Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Duvall's 142nd Place sidewalk - Phase 2

C-P-802(002)-1

C-P-802(002)-1
142nd Place sidewalk - Phase 2

275th Avenue NE to 278th Avenue NE

FY 2026 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $400,000

County: King   |   Legislative District: 45   |   Project Length: 0.15   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 11/21/2024

Project Information

Lead Agency DUVALL
Funding Year 2026
Program CSP
Current Phase Construction
Legislative District 45
Congressional District 8
Federal Route Number 9999
Project Length 0.15 mi.
ADT 0
Functional Class Local Access
Type of Work Pedestrian
Project Contact Benjamin Ressler
Contact Email benjamin.ressler@duvallwa.gov
TIB Engineer Greg Armstrong
Last Payment Date 11/21/2024
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   03/22/2024
Delayed Project Date 03/22/2027  
DAHP Assessment Date   07/21/2021
Predesign Approval
Design Approval 04/02/2024 03/29/2024
Bid Auth. Approval 05/14/2024 05/16/2024
Construction Approval 06/11/2024 06/13/2024
Project Closeout 12/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 8,902 11,642
Construction Contract 391,098 710,781
Other Construction 0 0
Total Construction 400,000 722,423
     
Total TIB Funding 400,000 722,423

Local Funding Partners

Funding Amount Percent
DUVALL 122,423 16.9%
WSDOT Funding 0 0.0%
CDBG  200,000 27.7%
 
 
 
 
 
 
 
Total Local Funding 322,423 44.6%

Project Description

NE 142nd Pl in this area is an unimproved, two lane residential roadway with gravel shoulders and open ditching that lacks any pedestrian features. This project consists of upgrading the roadway by installing 780' of 5'-wide sidewalk on NE 142nd Pl between 275th Ave NE and 278th Ave NE on the north side of the roadway, adding a shared use car and bicycle lane that transitions into a bike lane, and adding three designated parking stalls. A majority of the sidewalk will be separated from the travel lanes by planter

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments