Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Carnation's Tolt Middle School Sidewalk

C-P-801(002)-1

C-P-801(002)-1
Tolt Middle School Sidewalk

N Driveway to S Driveway

FY 2026 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $165,750

County: King   |   Legislative District: 12   |   Project Length: 0.09   |   TIB Engineer: Greg Armstrong   |   Last Payment Date:

Project Information

Lead Agency CARNATION
Funding Year 2026
Program CSP
Current Phase Construction
Legislative District 12
Congressional District 8
Federal Route Number 0203
Project Length 0.09 mi.
ADT 0
Functional Class Collector
Type of Work Pedestrian
Project Contact Lora Wilmes
Contact Email lora.wilmes@carnationwa.gov
TIB Engineer Greg Armstrong
Last Payment Date
Cultural Resource Assessment

Project Schedule

  Target Date Actual Date
Project Selection Date   05/13/2024
Delayed Project Date 05/13/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 06/15/2024 06/17/2024
Bid Auth. Approval 07/11/2024 07/12/2024
Construction Approval 08/27/2024 09/03/2024
Project Closeout 12/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 7,000 10,000
Right of Way 0 0
Total Design 7,000 10,000
     
Construction Engineering 20,900 30,507
Construction Contract 137,850 166,784
Other Construction 0 0
Total Construction 158,750 197,291
     
Total TIB Funding 165,750 207,291

Local Funding Partners

Funding Amount Percent
CARNATION 41,541 20.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 41,541 20.0%

Project Description

This project includes improvements to the pedestrian sidewalk immediately west of Tolt Middle School. The existing sidewalk is a raised asphalt pedestrian pathway against a concrete curb. The pathway includes two sections of sidewalk, spans two vehicle access points, and contains concrete, low slope pedestrian access points to each section (4 total). The existing facilities are in poor condition, and exhibit cracking, spalling concrete, uneven surfaces, uneven edges (trip hazards), and failed/delaminated ADA ramp warning plates. This project will include removal and wastehauling of theexisting pedestrian facilities, and installation of new concrete sidewalk, curb, gutter, and ADA compliant entry and exit ramps (2 each). The proposed facilities will be aligned with adjacent pedestrian walkfacilities and will be installed according to current Right-of-Way extents. There are existing stormwater and potable water utilities that will be affected, and these components will be adjusted as required to accommodate the new facilities. Asphalt pavement repair will also be included with the project asrequired to facilitate installation of the new facilities.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments