City of Kenmore's NE 170 Street ped/bike improvements

C-P-206(002)-1

C-P-206(002)-1
NE 170 Street ped/bike improvements

Juanita Drive to 72nd Avenue NE

FY 2026 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $212,888

County: King   |   Legislative District: 1   |   Project Length: 0.10   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 11/27/2024

Project Information

Lead Agency KENMORE
Funding Year 2026
Program CSP
Current Phase Construction
Legislative District 1, 1
Congressional District 1
Federal Route Number 2448
Project Length 0.10 mi.
ADT 0
Functional Class Principal
Type of Work Pedestrian
Project Contact John Vicente
Contact Email jvicente@kenmorewa.gov
TIB Engineer Greg Armstrong
Last Payment Date 11/27/2024
Cultural Resource Assessment

Project Schedule

  Target Date Actual Date
Project Selection Date   03/22/2024
Delayed Project Date 03/22/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 04/10/2024 04/16/2024
Bid Auth. Approval 04/10/2024 04/16/2024
Construction Approval 04/30/2024 04/26/2024
Project Closeout 12/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 16,800 24,000
Construction Contract 168,320 336,503
Other Construction 0 0
Total Construction 185,120 360,503
     
Funding Increase 27,768  
Total TIB Funding 212,888 360,503

Local Funding Partners

Funding Amount Percent
KENMORE 147,615 40.9%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 147,615 40.9%

Project Description

This project will provide sidewalk along the north side of NE 170th St from 72nd Ave NE to 70th Ave NE where existing sidewalk currently ends. The proposed sidewalk would meet minimum requirements for ADA (Americans with Disabilities Act) compliance. The existing R-turn only lane westbound on NE 170th will be changed to a buffered bike lane, the bike lane on the eastbound side of NE 170th will be extended west to the NE 170th intersection, and the existing bike lane near 72nd Ave NE will have a buffer added. These added bike lanes will connect the existing bike network on Juanita Dr/68th and the existing bike lanes east of 72nd St along Simonds Rd.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.