TIB Project Information

City of Maple Valley's Crosswalk safety RRFB

C-P-205(001)-1

C-P-205(001)-1
Crosswalk safety RRFB

Multiple Locations

FY 2026 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $130,600

County: King   |   Legislative District: 5   |   Project Length: 0.10   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 04/01/2025

Project Information

Lead Agency MAPLE VALLEY
Funding Year 2026
Program CSP
Current Phase Audit
Legislative District 5
Congressional District 8
Federal Route Number 1381
Project Length 0.10 mi.
ADT 0
Functional Class Local Access
Type of Work Pedestrian
Project Contact Steven Chen
Contact Email steven.chen@maplevalleywa.gov
TIB Engineer Greg Armstrong
Last Payment Date 04/01/2025
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   03/22/2024
Delayed Project Date 03/22/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 04/10/2024 04/11/2024
Bid Auth. Approval 04/11/2024 04/11/2024
Construction Approval 08/19/2024 08/07/2024
Project Closeout 03/31/2025 03/28/2025
Audit Date   04/01/2025
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 27,840 2,290
Right of Way 0 0
Total Design 27,840 2,290
     
Construction Engineering 27,840 5,429
Construction Contract 278,400 155,531
Other Construction 0 0
Total Construction 306,240 160,960
     
Funding Surplus - 203,480  
Total TIB Funding 130,600 163,250

Local Funding Partners

Funding Amount Percent
MAPLE VALLEY 32,650 20.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 32,650 20.0%

Project Description

Installs RRFB's at six locations 242nd PL SE SE 256th St, SE 280th St Glazier Park Elementary, SE 240th St 222nd Pl SE, Witte Road SE 248th St, Witte Road SE SE 254th Pl and 216th Ave SE SE 280th St

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments