Projects — TIB Project Information
TIB Project Information
City of Edmonds's Complete Streets Award
C-P-139(001)-1
C-P-139(001)-1
Complete Streets Award
Jan 2017 Selection
FY 2018 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $250,000
County: Snohomish | Legislative District: 21 | Project Length: 0.01 | TIB Engineer: Greg Armstrong | Last Payment Date: 07/06/2017
Project Information
Lead Agency | EDMONDS |
Funding Year | 2018 |
Program | CSP |
Current Phase | Audit |
Legislative District | 21 |
Congressional District | 7 |
Federal Route Number | 9999 |
Project Length | 0.01 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Pedestrian |
Project Contact | Hague, Ryan |
Contact Email | Ryan.Hague@edmondswa.gov |
TIB Engineer | Greg Armstrong |
Last Payment Date | 07/06/2017 |
Cultural Resource Assessment |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 02/06/2017 | |
Delayed Project Date | 07/01/2019 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/06/2017 | |
Bid Auth. Approval | 02/06/2017 | |
Construction Approval | 05/20/2017 | 06/08/2017 |
Project Closeout | 10/31/2018 | 07/03/2018 |
Audit Date | 07/16/2018 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 250,000 | 250,000 |
Other Construction | 0 | 0 |
Total Construction | 250,000 | 250,000 |
Total TIB Funding | 250,000 | 250,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
EDMONDS | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Complete Streets Workplan
Item | Type of Work | Date Added | Est. Cost | Actual Cost | Complete |
---|---|---|---|---|---|
Dayton Street Sidewalk enhancements | Pedestrian | Dec 2016 | $250,000 | $ 0 | |
Complete sidewalk enhnacements along Dayton Street between 3rd Avenue and 9th Avenue. Enhancements include replacement of failing sidewalk sections, removal of obstructions, ADA ramp upgrades and completes a short missing sidewalk link. | |||||
Sidewalk enhancement along 238th Street SE between SR 99 and SR 104 |
Pedestrian | Jan 2018 | $250,000 | $250,000 | |
This project will widen the 1000 linear foot of proposed sidewalk on the north side of 238th St. SW between SR 104 and SR 99 from 5' to 7, and complete pedestrian improvements to the existing island on the west side of the project limits (SR 104 @ 238th Sr. SW) |
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |