TIB Project Information

City of Everett's Complete Streets Award

C-P-138(001)-1

C-P-138(001)-1
Complete Streets Award

Jan 2017 Selection

FY 2018 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $250,000

County: Snohomish   |   Legislative District: 38   |   Project Length: 0.10   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 07/06/2017

Project Information

Lead Agency EVERETT
Funding Year 2018
Program CSP
Current Phase Audit
Legislative District 38
Congressional District 2
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class Collector
Type of Work Pedestrian
Project Contact Richard Tarry
Contact Email rtarry@everettwa.gov
TIB Engineer Greg Armstrong
Last Payment Date 07/06/2017
Cultural Resource Assessment

Project Schedule

  Target Date Actual Date
Project Selection Date   02/06/2017
Delayed Project Date 07/01/2019  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/06/2017
Bid Auth. Approval 02/15/2017
Construction Approval 03/31/2017 04/10/2017
Project Closeout 12/31/2019 01/27/2019
Audit Date   02/04/2020
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 250,000 250,000
Other Construction 0 0
Total Construction 250,000 250,000
     
Total TIB Funding 250,000 250,000

Local Funding Partners

Funding Amount Percent
EVERETT 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Complete Streets Workplan

Item Type of Work Date Added Est. Cost Actual Cost Complete
Regional Bicycle Network Link Bicycle Dec 2016 $140,000 $152,912
Design and construct a signed bicycle route that links dowtown bicycle lanes on Hoyt Avenue with the Interurban Regional Trail at 41st and Colby.
Hewitt Avenue Pedestrian Improvements Pedestrian Dec 2016 $75,000 $ 0
Construct pedestrian improvements associated with a planned Everett Massacre historic memorial
Bond Street to Terminal Avenue Pedestrian Dec 2016 $80,000 $75,777
Pedestrian improvements linking the Forgotten Creek Trailhead at Bond Street to the Terminal Avenue Bridge to enhance pedestrian waterfront access
19th Street Bike Lane Enhancements Dec 2016 $30,000 $91,330
Add signs and markings to the bike lanes on 19th Street linking Jackson Park to the downtown bike lanes.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments