Town of Ruston's Complete Streets Award
C-P-135(001)-1
C-P-135(001)-1
Complete Streets Award
Jan 2017 Selection
FY 2018 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $250,000
County: Pierce | Legislative District: 27 | Project Length: 0.10 | TIB Engineer: Greg Armstrong | Last Payment Date: 02/27/2017
Project Information
Lead Agency | RUSTON |
Funding Year | 2018 |
Program | CSP |
Current Phase | Audit |
Legislative District | 27 |
Congressional District | 6 |
Federal Route Number | 9999 |
Project Length | 0.10 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Pedestrian |
Project Contact | Rob White |
Contact Email | robw@rustonwa.org |
TIB Engineer | Greg Armstrong |
Last Payment Date | 02/27/2017 |
Cultural Resource Assessment |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 02/07/2017 | |
Delayed Project Date | 07/01/2019 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/07/2017 | |
Bid Auth. Approval | 02/15/2017 | |
Construction Approval | 02/15/2017 | 02/14/2017 |
Project Closeout | 01/15/2020 | 01/14/2020 |
Audit Date | 02/04/2020 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 250,000 | 250,000 |
Other Construction | 0 | 0 |
Total Construction | 250,000 | 250,000 |
Total TIB Funding | 250,000 | 250,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
RUSTON | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Complete Streets Workplan
Item | Type of Work | Date Added | Est. Cost | Actual Cost | Complete |
---|---|---|---|---|---|
Pearl Street Ped. Improvements | Pedestrian; Bicycle | Jan 2017 | $180,000 | $ 0 | |
Design/Construct bulb outs where practical, narrow lanes, realigning on street parking, Installing a bike lane from 49th to 50th and widen sidewalks. | |||||
Winnifred Street Bridge Ped. Safety | Planning; Pedestrian | Jan 2017 | $250,000 | $250,000 | |
Current pedestrian crossings within the intersection of Winnifred and 51st Street requires pedestrians to cross travel lanes which is larger than necessary, Design/Construct appropriate pedestrian enhnancements, (i.e. bulb-outs, bollards, crosswalk markings, etc) at the intersection of 51st and Winnifred and adjacent Winnfred Street Bridge, and within optional nearby intersections depending on bid results and as funding allows, (see attached estimate and map). |
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |