City of Tacoma's McKinley overlook complete streets

C-P-128(003)-1

C-P-128(003)-1
McKinley overlook complete streets

East E Street to East F Street

FY 2026 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $469,532

County: Pierce   |   Legislative District: 29   |   Project Length: 0.25   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 10/01/2024

Project Information

Lead Agency TACOMA
Funding Year 2026
Program CSP
Current Phase Construction
Legislative District 29
Congressional District 10
Federal Route Number 9999
Project Length 0.25 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Pedestrian
Project Contact Clara Dubow
Contact Email cdubow@cityoftacoma.org
TIB Engineer Greg Armstrong
Last Payment Date 10/01/2024
Cultural Resource Assessment

Project Schedule

  Target Date Actual Date
Project Selection Date   03/22/2024
Delayed Project Date 03/22/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 03/22/2024 03/28/2024
Bid Auth. Approval 04/30/2024 04/24/2024
Construction Approval 05/21/2024 05/30/2024
Project Closeout 02/28/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 62,530 45,894
Right of Way 0 0
Total Design 62,530 45,894
     
Construction Engineering 62,530 87,787
Construction Contract 255,509 583,329
Other Construction 27,720 5,073
Total Construction 345,759 676,189
     
Funding Increase 61,243  
Total TIB Funding 469,532 722,083

Local Funding Partners

Funding Amount Percent
TACOMA 252,551 35.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 252,551 35.0%

Project Description

This project will be reducing the existing roadway width to provide a sidewalk with planters, illumination, and various amenities and artwork. ADA-compliant curb ramps and parking has also been incorporated. The Overlook is at a very high vantage point, and this sidewalk connects the Overlook to a stairway that leads down to the bottom of the hill, where it ties into a complete-streets corridor. This connecting street, East McKinley Way, provides direct access to the neighborhood businesses to the south, promoting community involvement and creating a cohesive plan for future connections to the west and the overall business district of the McKinley neighborhood. East McKinley Way also provides access to the Dome district to the west, which is frequented by people looking to use the main transit hub as well as attend events at the Tacoma Dome and Freighthouse Square.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.