Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Tacoma's Complete Streets Award

C-P-128(002)-1

C-P-128(002)-1
Complete Streets Award

March 2022 Selection

FY 2023 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $450,000

County: Pierce   |   Legislative District: 27   |   Project Length: 0.63   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 06/07/2022

Project Information

Lead Agency TACOMA
Funding Year 2023
Program CSP
Current Phase Construction
Legislative District 27
Congressional District 6
Federal Route Number 3198
Project Length 0.63 mi.
ADT 5,550
Functional Class Collector
Type of Work Pedestrian
Project Contact Chris Storey
Contact Email cstorey@cityoftacoma.org
TIB Engineer Greg Armstrong
Last Payment Date 06/07/2022
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   03/28/2022
Delayed Project Date 03/28/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 05/01/2022 04/11/2022
Bid Auth. Approval 05/01/2022 04/11/2022
Construction Approval 05/01/2022 04/11/2022
Project Closeout 06/30/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 450,000 450,000
Other Construction 0 0
Total Construction 450,000 450,000
     
Total TIB Funding 450,000 450,000

Local Funding Partners

Funding Amount Percent
TACOMA 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Complete Streets Workplan

Item Type of Work Date Added Est. Cost Actual Cost Complete
Cement Concrete Sidewalk Mar 2022 $246,000 $ 0
Replace existing narrow, damaged, and incomplete sidewalk with new sidewalk on both sides of the road of Cement Concrete Sidewalk varying width from 6 feet to 7 feet - based on varying right of way width. Includes upgrading Pierce Transit bus stops on Portland Avenue.
Cement Concrete Curb Ramp & Cement Concrete Pedestrian Curb Mar 2022 $181,050 $ 0
Install ADA curb ramps where none currently exist and Cement Concrete Curb Ramp & upgrade existing non-compliant ramps. The project will Cement Concrete Pedestrian Curb install new ramps at all intersections within the project limits.
Crushed Surfacing Top Course & HMA CL 3/8" PG 58H-22
for Separated Bike Lane
Mar 2022 $22,950 $ 0
Construct a raised separated directional bike lane on Crushed Surfacing Top Course & each side of the roadway. The bike lane will be installed HMA CL 3/8" PG 58H-22 for at the same elevation and alongside of the sidewalk using asphalt to distinguish it from the concrete sidewalk. Separated Bike Lane

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments