Projects — TIB Project Information
TIB Project Information
City of Tacoma's Complete Streets Award
C-P-128(002)-1
C-P-128(002)-1
Complete Streets Award
March 2022 Selection
FY 2023 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $450,000
County: Pierce | Legislative District: 27 | Project Length: 0.63 | TIB Engineer: Greg Armstrong | Last Payment Date: 06/07/2022
Project Information
Lead Agency | TACOMA |
Funding Year | 2023 |
Program | CSP |
Current Phase | Construction |
Legislative District | 27 |
Congressional District | 6 |
Federal Route Number | 3198 |
Project Length | 0.63 mi. |
ADT | 5,550 |
Functional Class | Collector |
Type of Work | Pedestrian |
Project Contact | Chris Storey |
Contact Email | cstorey@cityoftacoma.org |
TIB Engineer | Greg Armstrong |
Last Payment Date | 06/07/2022 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 03/28/2022 | |
Delayed Project Date | 03/28/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 05/01/2022 | 04/11/2022 |
Bid Auth. Approval | 05/01/2022 | 04/11/2022 |
Construction Approval | 05/01/2022 | 04/11/2022 |
Project Closeout | 06/30/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 450,000 | 450,000 |
Other Construction | 0 | 0 |
Total Construction | 450,000 | 450,000 |
Total TIB Funding | 450,000 | 450,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
TACOMA | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Complete Streets Workplan
Item | Type of Work | Date Added | Est. Cost | Actual Cost | Complete |
---|---|---|---|---|---|
Cement Concrete Sidewalk | Mar 2022 | $246,000 | $ 0 | ||
Replace existing narrow, damaged, and incomplete sidewalk with new sidewalk on both sides of the road of Cement Concrete Sidewalk varying width from 6 feet to 7 feet - based on varying right of way width. Includes upgrading Pierce Transit bus stops on Portland Avenue. | |||||
Cement Concrete Curb Ramp & Cement Concrete Pedestrian Curb | Mar 2022 | $181,050 | $ 0 | ||
Install ADA curb ramps where none currently exist and Cement Concrete Curb Ramp & upgrade existing non-compliant ramps. The project will Cement Concrete Pedestrian Curb install new ramps at all intersections within the project limits. | |||||
Crushed Surfacing Top Course & HMA CL 3/8" PG 58H-22 for Separated Bike Lane |
Mar 2022 | $22,950 | $ 0 | ||
Construct a raised separated directional bike lane on Crushed Surfacing Top Course & each side of the roadway. The bike lane will be installed HMA CL 3/8" PG 58H-22 for at the same elevation and alongside of the sidewalk using asphalt to distinguish it from the concrete sidewalk. Separated Bike Lane |
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |