Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of SeaTac's Complete Streets Award

C-P-121(001)-1

C-P-121(001)-1
Complete Streets Award

March 2022 Selection

FY 2023 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $600,000

County: King   |   Legislative District: 33   |   Project Length: 0.00   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 06/07/2022

Project Information

Lead Agency SEATAC
Funding Year 2023
Program CSP
Current Phase Construction
Legislative District 33
Congressional District 9
Federal Route Number 9999
Project Length 0.00 mi.
ADT 0
Functional Class Collector
Type of Work Pedestrian
Project Contact Florendo  Cabudol
Contact Email fcabudol@seatacwa.gov
TIB Engineer Greg Armstrong
Last Payment Date 06/07/2022
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   03/28/2022
Delayed Project Date 03/28/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 05/01/2022 05/02/2022
Bid Auth. Approval 05/01/2022 05/02/2022
Construction Approval 05/01/2022 05/02/2022
Project Closeout 12/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 600,000 600,000
Other Construction 0 0
Total Construction 600,000 600,000
     
Total TIB Funding 600,000 600,000

Local Funding Partners

Funding Amount Percent
SEATAC 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Complete Streets Workplan

Item Type of Work Date Added Est. Cost Actual Cost Complete
River Ridge Elementary School safe route to school project Mar 2022 $300,000 $ 0
Project to construct sidewalk along east side of Military Rd S between River Ridge Elementary School and new Alexan Gateway Apartment (23040, Military Road S Kent, WA 98032; 283 units). SeaTac is partnering with Kent School District and City of Kent to construct sidewalk and associated appurtanences to provide a safe walking route for students accessing the new elementary
34th Avenue South, Phase 2 Mar 2022 $300,000 $ 0
Project to reconstruct roadway to meet collector arterial standards. Construct sidewalk drainage, curb, gutter, shared bicycle facilities, street/pedestrian lighting. Install traffic calming measures and underground utility  lines.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments