No sidewalks existing along the following segments Seattle Boulevard S - 3rd Ave SW tp 2nd Ave SW 2nd Avenue SW - Seattle Blvd S- Glacier Ave SW 2nd Avenue SE - Pacific Ave S to Cedar Lane Cedar Lane - 2nd Ave SE to 1st Ave E 1st Place SE - Cedar Lane to EOR
Projects — TIB Project Information
TIB Project Information
City of Pacific's New sidewalks
C-P-117(001)-1
C-P-117(001)-1
New sidewalks
Multiple Locations
FY 2026 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $620,713
County: King/Pierce | Legislative District: 30 | Project Length: 1.00 | TIB Engineer: Greg Armstrong | Last Payment Date: 10/28/2024
Project Information
Lead Agency | PACIFIC |
Funding Year | 2026 |
Program | CSP |
Current Phase | Construction |
Legislative District | 30 |
Congressional District | 9 |
Federal Route Number | 9999 |
Project Length | 1.00 mi. |
ADT | 0 |
Functional Class | Local Access |
Type of Work | Pedestrian |
Project Contact | Rick Gehrke |
Contact Email | rgehrke@ci.pacific.wa.us |
TIB Engineer | Greg Armstrong |
Last Payment Date | 10/28/2024 |
Cultural Resource Assessment |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 03/22/2024 | |
Delayed Project Date | 03/22/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 03/22/2024 | 03/25/2024 |
Bid Auth. Approval | 06/14/2024 | 06/03/2024 |
Construction Approval | 07/01/2024 | 07/01/2024 |
Project Closeout | 12/31/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 5,100 | 0 |
Right of Way | 0 | 0 |
Total Design | 5,100 | 0 |
Construction Engineering | 5,100 | 167,187 |
Construction Contract | 529,550 | 834,537 |
Other Construction | 0 | 0 |
Total Construction | 534,650 | 1,001,724 |
Funding Increase | 80,963 | |
Total TIB Funding | 620,713 | 1,001,724 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
PACIFIC | 381,011 | 38.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 381,011 | 38.0% |
Project Description
'Project provides sidewalks on residential streets without pedestrian facilities or shoulders, and connectsgaps in sidewalk network, including gaps to connect residential neighborhoods to the Interurban Trail. Additional trailhead parking at Interurban Trail will improve access to the trail to users who live furtheraway. The Planning Commission & City Council are 100% behind these projects.'
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |