City of Federal Way's SR 99 pedestrian improvements
C-P-113(002)-1
C-P-113(002)-1
SR 99 pedestrian improvements
S 304th Street to S 308th Street
FY 2026 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $120,800
County: King | Legislative District: 30 | Project Length: 0.10 | TIB Engineer: Greg Armstrong | Last Payment Date: 09/13/2024
Project Information
Lead Agency | FEDERAL WAY |
Funding Year | 2026 |
Program | CSP |
Current Phase | Construction |
Legislative District | 30 |
Congressional District | 8 |
Federal Route Number | 0099 |
Project Length | 0.10 mi. |
ADT | 0 |
Functional Class | Principal |
Type of Work | Pedestrian |
Project Contact | Rick Perez, |
Contact Email | rick.perez@cityoffederalway.com |
TIB Engineer | Greg Armstrong |
Last Payment Date | 09/13/2024 |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 03/22/2024 | |
Delayed Project Date | 03/22/2027 | |
DAHP Assessment Date | 07/25/2024 | |
Predesign Approval | ||
Design Approval | 04/10/2024 | 04/22/2024 |
Bid Auth. Approval | 07/15/2024 | 07/23/2024 |
Construction Approval | 08/10/2024 | 08/08/2024 |
Project Closeout | 12/31/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 4,000 | 15,000 |
Right of Way | 0 | 0 |
Total Design | 4,000 | 15,000 |
Construction Engineering | 4,000 | 15,000 |
Construction Contract | 112,800 | 121,000 |
Other Construction | 0 | 0 |
Total Construction | 116,800 | 136,000 |
Total TIB Funding | 120,800 | 151,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
FEDERAL WAY | 30,200 | 20.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 30,200 | 20.0% |
Project Description
The project would attempt to make improvements to pedestrian mobility through improved streetlighting, median fencing to encourage crossing at interesections, and reducing speeds during school ingress and egress periods along Pacific Highway S between S 304th Street and S 308th Street via a 30 MPH advisory school speed zone. Additionally, the City will replace luminaire heads at the intersection of S 308 St and SR 99, as well as the 1st one on each side of the intersection and each side of SR 99 away from the intersection (8 total) with higher wattage LEDs to improve pedestrian visability. Red Light Indicator lights will also be installed on the signal heads at both intersections within this corridor to provide easier way for police to enforce red-light running. As soon as weather permits, the City will also refresh all crosswalk markings and stop lines at S 308 St and SR 99. There are no proposed changes to channelization so it is anticipated that WSDOT's concurrence is not required.
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |