Projects — TIB Project Information
TIB Project Information
Snohomish County's Pedestrian improvements
C-P-031(001)-1
C-P-031(001)-1
Pedestrian improvements
Multiple Locations
FY 2026 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $144,998
County: Snohomish | Legislative District: 1 | Project Length: 0.50 | TIB Engineer: Greg Armstrong | Last Payment Date: 11/05/2024
Project Information
Lead Agency | SNOHOMISH COUNTY |
Funding Year | 2026 |
Program | CSP |
Current Phase | Construction |
Legislative District | 1 |
Congressional District | 1 |
Federal Route Number | 9999 |
Project Length | 0.50 mi. |
ADT | 0 |
Functional Class | Local Access |
Type of Work | Pedestrian |
Project Contact | Ellora Larson |
Contact Email | Ellora.Larson@snoco.org |
TIB Engineer | Greg Armstrong |
Last Payment Date | 11/05/2024 |
Cultural Resource Assessment |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 03/22/2024 | |
Delayed Project Date | 03/22/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 04/07/2024 | 04/02/2024 |
Bid Auth. Approval | 08/01/2024 | 04/02/2024 |
Construction Approval | 09/01/2024 | 05/30/2024 |
Project Closeout | 12/31/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 31,249 | 15,380 |
Right of Way | 0 | 0 |
Total Design | 31,249 | 15,380 |
Construction Engineering | 24,998 | 12,300 |
Construction Contract | 312,453 | 153,701 |
Other Construction | 0 | 0 |
Total Construction | 337,451 | 166,001 |
Funding Surplus | - 223,702 | |
Total TIB Funding | 144,998 | 181,381 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
SNOHOMISH COUNTY | 36,383 | 20.1% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 36,383 | 20.1% |
Project Description
The four RRFB locations bundled under this application include 51st Ave SE and 123rd St SE Discovery Elementary Crossing on Meridian Ave Fernwood Elementary at 197th St SW & Jewell Rd and Fernwood Elementary 39th Ave SE Midblock. The addition of RRFBs proposed at the request of community will enhance safety and provide a solution at these crossings. The installation of rectangular rapid flashing beacons at the various locations throughout the County will bring further visibility and awareness of pedestrians crossing which will improve access and usability of pedestrian facilities. Mays Pond ADA Bus Stop Upgrades bundled with this application was identified in the ADA Transition Plan that resulted from the community outreach and engagement. Cross slopes for the Mays Pond Bus Stops do not meet standard and there are currently no alighting areas to allow wheelchair users to board and deboard the buses. This project will improve accessibility to transit and pedestrian access by providing ADA compliant launch pads at bus stops in the Mays Pond area.
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |