Projects — TIB Project Information
TIB Project Information
Pierce County's Complete Streets Award
C-P-027(001)-1
C-P-027(001)-1
Complete Streets Award
Jan 2017 Selection
FY 2018 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $250,000
County: Pierce | Legislative District: 2 | Project Length: 0.10 | TIB Engineer: Greg Armstrong | Last Payment Date: 07/06/2017
Project Information
Lead Agency | PIERCE COUNTY |
Funding Year | 2018 |
Program | CSP |
Current Phase | Audit |
Legislative District | 2, 25, 27, 28, 29 |
Congressional District | 6, 10 |
Federal Route Number | 9999 |
Project Length | 0.10 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Pedestrian |
Project Contact | Clint Ritter |
Contact Email | clint.ritter@piercecountywa.gov |
TIB Engineer | Greg Armstrong |
Last Payment Date | 07/06/2017 |
Cultural Resource Assessment |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 02/07/2017 | |
Delayed Project Date | 07/01/2019 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/07/2017 | |
Bid Auth. Approval | 02/15/2017 | |
Construction Approval | 02/15/2017 | 03/08/2017 |
Project Closeout | 09/30/2018 | 09/07/2018 |
Audit Date | 09/11/2018 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 250,000 | 250,000 |
Other Construction | 0 | 0 |
Total Construction | 250,000 | 250,000 |
Total TIB Funding | 250,000 | 250,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
PIERCE COUNTY | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Complete Streets Workplan
Item | Type of Work | Date Added | Est. Cost | Actual Cost | Complete |
---|---|---|---|---|---|
Sidewalks | Pedestrian | Dec 2016 | $100,000 | $100,000 | |
Design/Construct sidewalk on C St. between Lafayette St. S and 112th St. S. | |||||
Curb Ramps | Pedestrian | Dec 2016 | $150,000 | $150,000 | |
Design/Reconstruct curb ramps along C St. S from the Lafayette St. S Intersection to the Intersection with Wheeler St. S. |
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |