Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

Town of Naches's Complete Streets Award

C-E-944(001)-1

C-E-944(001)-1
Complete Streets Award

Jan 2017 Selection

FY 2018 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $125,000

County: Yakima   |   Legislative District: 14   |   Project Length: 0.10   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 02/27/2017

Project Information

Lead Agency NACHES
Funding Year 2018
Program CSP
Current Phase Audit
Legislative District 14
Congressional District 4
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Pedestrian
Project Contact Jeff Ranger
Contact Email jeff.ranger@co.yakima.wa.us
TIB Engineer Jonathan Heusman
Last Payment Date 02/27/2017
Cultural Resource Assessment

Project Schedule

  Target Date Actual Date
Project Selection Date   02/07/2017
Delayed Project Date 07/01/2019  
DAHP Assessment Date  
Predesign Approval 12/21/2016
Design Approval 02/15/2017
Bid Auth. Approval 02/15/2017
Construction Approval 02/15/2017 02/07/2017
Project Closeout 12/01/2018 03/12/2018
Audit Date   03/13/2018
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 125,000 125,000
Other Construction 0 0
Total Construction 125,000 125,000
     
Total TIB Funding 125,000 125,000

Local Funding Partners

Funding Amount Percent
NACHES 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Complete Streets Workplan

Item Type of Work Date Added Est. Cost Actual Cost Complete
Naches Trail Pathway Pedestrian Lighting Pedestrian; Bicycle Dec 2016 $122,000 $150,180
Design and installlation of pedestrian lighting along the Naches Trail (Yakima Greenway) beginning at Allan Road and heading west into town.
Naches Trailway Benches and Trash Receptacles Pedestrian; Bicycle Dec 2016 $3,000 $ 0
Purchase and installation of benches and trash receptacles along the Naches Trail Pathway

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.