 Projects — TIB Project Information

TIB Project Information

City of Moxee's Pedestrian Improvements

C-E-943(002)-1

C-E-943(002)-1
Pedestrian Improvements

Multiple Locations

FY 2026 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $332,337

County: Yakima   |   Legislative District: 15   |   Project Length: 0.25   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 03/17/2025

Project Information

Lead Agency MOXEE
Funding Year 2026
Program CSP
Current Phase Audit
Legislative District 15
Congressional District 4
Federal Route Number 9999
Project Length 0.25 mi.
ADT 0
Functional Class Minor
Type of Work Pedestrian
Project Contact Jeff Burkett
Contact Email jeff.burkett@co.yakima.wa.us
TIB Engineer Jonathan Heusman
Last Payment Date 03/17/2025
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   03/22/2024
Delayed Project Date 03/22/2027  
DAHP Assessment Date   05/08/2024
Predesign Approval
Design Approval 04/22/2024 04/22/2024
Bid Auth. Approval 07/23/2024 07/19/2024
Construction Approval 08/22/2024 09/13/2024
Project Closeout 12/31/2024 03/04/2025
Audit Date   03/17/2025
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 48,222 53,580
Right of Way 0 0
Total Design 48,222 53,580
     
Construction Engineering 55,107 43,356
Construction Contract 344,430 285,308
Other Construction 0 0
Total Construction 399,537 328,664
     
Funding Increase 15,378  
Funding Surplus - 130,800  
Total TIB Funding 332,337 382,244

Local Funding Partners

Funding Amount Percent
MOXEE 49,907 13.1%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 49,907 13.1%

Project Description

Construct sidewalk, curb, and gutter to fill gap from Seattle Avenue to Rivard Road. Also install 5 RRFB's at intersections that are major routes for pedestrians and bicyclists, including safe routes to school.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.