TIB Project Information

City of Mabton's Complete Streets Award

C-E-942(002)-1

C-E-942(002)-1
Complete Streets Award

March 2022 Selection

FY 2023 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $75,000

County: Yakima   |   Legislative District: 15   |   Project Length: 0.10   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 06/07/2022

Project Information

Lead Agency MABTON
Funding Year 2023
Program CSP
Current Phase Construction
Legislative District 15
Congressional District 4
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Pedestrian
Project Contact Sylvia Sanchez
Contact Email sylvia.sanchez@co.yakima.wa.us
TIB Engineer Jonathan Heusman
Last Payment Date 06/07/2022
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   03/25/2022
Delayed Project Date 03/25/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 04/30/2022 04/07/2022
Bid Auth. Approval 04/30/2022 04/07/2022
Construction Approval 04/30/2022 04/07/2022
Project Closeout 12/15/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 75,000 75,000
Other Construction 0 0
Total Construction 75,000 75,000
     
Total TIB Funding 75,000 75,000

Local Funding Partners

Funding Amount Percent
MABTON 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Complete Streets Workplan

Item Type of Work Date Added Est. Cost Actual Cost Complete
RRFB at N 5th Street and B Street Pedestrian Mar 2022 $25,000 $25,000
Installation of a Rectangular Rapid Flashing Beacon signal system at the intersection of N 5th St. and B St.
Transit Stop and Aesthetic Improvements Transit; Aesthetics Mar 2022 $50,000 $50,000
Transit Stop improvements at Governor's Park (future Park N Ride Facility) including bus stop and other aesthetic improvements.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments