Projects — TIB Project Information
TIB Project Information
City of Cle Elum's Complete Streets Award
C-E-930(003)-1
C-E-930(003)-1
Complete Streets Award
March 2022 Selection
FY 2023 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $350,000
County: Kittitas | Legislative District: 13 | Project Length: 0.43 | TIB Engineer: Jonathan Heusman | Last Payment Date: 06/07/2022
Project Information
Lead Agency | CLE ELUM |
Funding Year | 2023 |
Program | CSP |
Current Phase | Construction |
Legislative District | 13 |
Congressional District | 8 |
Federal Route Number | P190 |
Project Length | 0.43 mi. |
ADT | 0 |
Functional Class | Principal |
Type of Work | Reconstruction |
Project Contact | Rob Omans |
Contact Email | romans@cleelum.gov |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 06/07/2022 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 03/28/2022 | |
Delayed Project Date | 03/28/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 04/30/2022 | 04/11/2022 |
Bid Auth. Approval | 04/30/2022 | 04/11/2022 |
Construction Approval | 04/30/2022 | 04/11/2022 |
Project Closeout | 12/31/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 350,000 | 350,000 |
Other Construction | 0 | 0 |
Total Construction | 350,000 | 350,000 |
Total TIB Funding | 350,000 | 350,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
CLE ELUM | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Complete Streets Workplan
Item | Type of Work | Date Added | Est. Cost | Actual Cost | Complete |
---|---|---|---|---|---|
First Street Downtown Revitalization Phases 3A and 3B | Pedestrian; Aesthetics | Mar 2022 | $350,000 | $306,000 | |
The combined First Street Downtown Revitalization Phases 3A and 3B project will include improvements on the south side of First Street between Billings Avenue and Oakes Avenue, intersection improvements to the northwest, southwest and northeast corners of the First Street and Oakes Avenue intersection, improvements on the north side of First Street between Oakes Avenue and Pennsylvania Avenue, improvements on the north side of First Street between Pennsylvania Avnue and Harris Avenue, and intersection improvements to the northwest corner of the First Street and Harris Avenue intersection. Improvements include new bulbouts, 30-degree angled parking, pavement markings with reduced lane widths, street signage with decorative pole provisions, curb and gutter, wide sidewalks with scoring patterns, ADA curb ramps, pedestrian and street illumination, hangining basket brackets, undergrounding utilities, planters with trees and shrubs based on adopted landscape and urban design treatmentes, irrigation system, and site furnishings, including benches, bike racks, relocating existing coal carts, and trash recepticals. | |||||
Safe Streets and Roads for All - Safety Action Plan and Program Action Plan |
Planning | Mar 2024 | $44,000 | $ 0 | |
The City will be developing a Safety Action Plan and complete an American Disability Act (ADA) Self Evaluation and Program Access Plan. The City received a Safe Streets and Roads for All (SS4A) grant award for this effort, which includes a 20% match requirement by the City. The Complete Streets award will serve as the City's match. The Safety Action Plan will prepare strategy to eliminate roadway fatalities and serious injury. The ADA Self Evaluation and Program Access Plan will assess existing public infrastructure for compliance with ADA standards, and identify future programs and projects necessary for ADA compliance. |
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |