No multi-use path to meet pedestrian demands.
Projects — TIB Project Information
TIB Project Information
City of Cle Elum's 2nd Street multi-use path
C-E-930(004)-1
C-E-930(004)-1
2nd Street multi-use path
Pennsylvania Avenue toward Short Avenue
FY 2026 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $500,000
County: Kittitas | Legislative District: 13 | Project Length: 0.28 | TIB Engineer: Jonathan Heusman | Last Payment Date: 02/27/2025
Project Information
| Lead Agency | CLE ELUM |
| Funding Year | 2026 |
| Program | CSP |
| Current Phase | Audit |
| Legislative District | 13 |
| Congressional District | 8 |
| Federal Route Number | 9999 |
| Project Length | 0.28 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Pedestrian |
| Project Contact | Rob Omans |
| Contact Email | romans@cleelum.gov |
| TIB Engineer | Jonathan Heusman |
| Last Payment Date | 02/27/2025 |
| Cultural Resource Assessment | CRA |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 03/22/2024 | |
| Delayed Project Date | 03/22/2027 | |
| DAHP Assessment Date | 11/18/2021 | |
| Predesign Approval | ||
| Design Approval | 03/22/2024 | 04/12/2024 |
| Bid Auth. Approval | 04/30/2024 | 04/23/2024 |
| Construction Approval | 05/31/2024 | 05/27/2024 |
| Project Closeout | 05/30/2025 | 04/16/2025 |
| Audit Date | 04/16/2025 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 80,000 | 90,363 |
| Construction Contract | 420,000 | 485,037 |
| Other Construction | 0 | 1,712 |
| Total Construction | 500,000 | 577,112 |
| Total TIB Funding | 500,000 | 577,112 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| CLE ELUM | 39,028 | 6.8% |
| WSDOT Funding | 0 | 0.0% |
| McCann Trucking LLC | 38,083 | 6.6% |
| Total Local Funding | 77,111 | 13.4% |
Project Description
Construct a multi-use, paved pathway that will meet demands for walking and rolling as alternatives to auto-centric transportation along the South side of 2nd Street from Pennsylvania Ave as far east as they are able to construct. This project will add on to the Phase 1 Second Street Pathway project that TIB funded in 2023.
Existing Condition
Project Benefits
- There is no continuity to the sidewalk system and its current state does not ensure unobstructed non-motorized mobility for people of all abilities.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||