Existing sidewalk and ramps are not ADA compliant
Projects — TIB Project Information
TIB Project Information
City of Dayton's S. 4th Street sidewalk
C-E-924(002)-1
C-E-924(002)-1
S. 4th Street sidewalk
E Main Street to Day Street
FY 2026 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $463,811
County: Columbia | Legislative District: 9 | Project Length: 0.52 | TIB Engineer: Jonathan Heusman | Last Payment Date: 11/15/2024
Project Information
Lead Agency | DAYTON |
Funding Year | 2026 |
Program | CSP |
Current Phase | Construction |
Legislative District | 9 |
Congressional District | 5 |
Federal Route Number | A070 |
Project Length | 0.52 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Pedestrian |
Project Contact | Ryan Paulson |
Contact Email | rpaulson@daytonwa.com |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 11/15/2024 |
Cultural Resource Assessment | IDP |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 03/22/2024 | |
Delayed Project Date | 03/22/2027 | |
DAHP Assessment Date | 08/23/2024 | |
Predesign Approval | ||
Design Approval | 05/22/2024 | 04/24/2024 |
Bid Auth. Approval | 08/15/2024 | 08/22/2024 |
Construction Approval | 09/15/2024 | 09/12/2024 |
Project Closeout | 12/01/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 57,000 | 120,000 |
Right of Way | 0 | 0 |
Total Design | 57,000 | 120,000 |
Construction Engineering | 57,000 | 60,000 |
Construction Contract | 487,350 | 313,222 |
Other Construction | 95,000 | 0 |
Total Construction | 639,350 | 373,222 |
Funding Surplus | - 232,539 | |
Total TIB Funding | 463,811 | 493,222 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
DAYTON | 29,411 | 6.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 29,411 | 6.0% |
Project Description
The proposed project will replace all ADA ramps in the project area, add sidewalk on the east side of S 4th Street between Clay Street and Main Street, and replace damaged sidewalk within the project limits. This project will create a safer and more accessible pedestrian route while preparing 4th Street for future street improvement projects. Construction for the sidewalks and ADA ramps will consist of concrete work, asphalt repair, landscaping, and painting crosswalk lines. Project will also complete roadway rehabilitation work using federal funds which may push construction out to 2025. City secured additional federal funding of $1.6 million and will be extending the sidewalk work limits further south to Day Street and will also be overlaying S 4th Street from Main Street to the South City Limits using those funds. Design of that additional work will be funded by this project.
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |