City of Dayton's Complete Streets Award
C-E-924(001)-1
C-E-924(001)-1
Complete Streets Award
March 2022 Selection
FY 2023 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $80,000
County: Columbia | Legislative District: 16 | Project Length: 0.90 | TIB Engineer: Jonathan Heusman | Last Payment Date: 06/07/2022
Project Information
Lead Agency | DAYTON |
Funding Year | 2023 |
Program | CSP |
Current Phase | Construction |
Legislative District | 16 |
Congressional District | 5 |
Federal Route Number | 0012 |
Project Length | 0.90 mi. |
ADT | 0 |
Functional Class | Principal |
Type of Work | Pedestrian |
Project Contact | Zac Weatherford |
Contact Email | zweatherford@daytonwa.com |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 06/07/2022 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 03/25/2022 | |
Delayed Project Date | 03/25/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 04/30/2022 | 04/07/2022 |
Bid Auth. Approval | 04/30/2022 | 04/07/2022 |
Construction Approval | 04/30/2022 | 04/07/2022 |
Project Closeout | 12/31/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 80,000 | 80,000 |
Other Construction | 0 | 0 |
Total Construction | 80,000 | 80,000 |
Total TIB Funding | 80,000 | 80,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
DAYTON | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Complete Streets Workplan
Item | Type of Work | Date Added | Est. Cost | Actual Cost | Complete |
---|---|---|---|---|---|
Priority 2 - Main Street Sidewalk Repairs | Pedestrian | Mar 2022 | $80,000 | $80,000 | |
Remove and replace failed and heaved sidewalk panels on Main Street in downtown Dayton. |
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |