TIB Project Information

City of Airway Heights's Complete Streets Award

C-E-893(001)-1

C-E-893(001)-1
Complete Streets Award

Jan 2017 Selection

FY 2018 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $250,000

County: Spokane   |   Legislative District: 6   |   Project Length: 0.10   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 05/01/2017

Project Information

Lead Agency AIRWAY HEIGHTS
Funding Year 2018
Program CSP
Current Phase Audit
Legislative District 6
Congressional District 5
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class Local Access
Type of Work Pedestrian
Project Contact Kevin Anderson
Contact Email kanderson@cawh.org
TIB Engineer Andrew Beagle
Last Payment Date 05/01/2017
Cultural Resource Assessment

Project Schedule

  Target Date Actual Date
Project Selection Date   01/27/2017
Delayed Project Date 07/01/2019  
DAHP Assessment Date  
Predesign Approval
Design Approval
Bid Auth. Approval
Construction Approval 03/01/2017 04/20/2017
Project Closeout 09/01/2019 08/08/2019
Audit Date   10/31/2019
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 250,000 250,000
Other Construction 0 0
Total Construction 250,000 250,000
     
Total TIB Funding 250,000 250,000

Local Funding Partners

Funding Amount Percent
AIRWAY HEIGHTS 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Complete Streets Workplan

Item Type of Work Date Added Est. Cost Actual Cost Complete
Prepare Complete Streets Plan Planning Jan 2017 $50,000 $ 0
Prepare plan that identifies improvements needed to provide for non-motorized transportation and other Complete Streets elements.
Sidewalk Ramp Replacement Pedestrian Feb 2017 $250,000 $250,000
Replace approximately 36 non-compliant curb ramps at various locations throughout the city.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments