Current Phase : Audit
Total TIB Funding : $250,000
County: Spokane | Legislative District: 6 | Project Length: 0.10 | TIB Engineer: Andrew Beagle | Last Payment Date: 05/01/2017
Project Information
Lead Agency | AIRWAY HEIGHTS |
Funding Year | 2018 |
Program | CSP |
Current Phase | Audit |
Legislative District | 6 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.10 mi. |
ADT | 0 |
Functional Class | Local Access |
Type of Work | Pedestrian |
Project Contact | Kevin Anderson |
Contact Email | kanderson@cawh.org |
TIB Engineer | Andrew Beagle |
Last Payment Date | 05/01/2017 |
Cultural Resource Assessment |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 01/27/2017 | |
Delayed Project Date | 07/01/2019 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | ||
Bid Auth. Approval | ||
Construction Approval | 03/01/2017 | 04/20/2017 |
Project Closeout | 09/01/2019 | 08/08/2019 |
Audit Date | 10/31/2019 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 250,000 | 250,000 |
Other Construction | 0 | 0 |
Total Construction | 250,000 | 250,000 |
Total TIB Funding | 250,000 | 250,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
AIRWAY HEIGHTS | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Complete Streets Workplan
Item | Type of Work | Date Added | Est. Cost | Actual Cost | Complete |
---|---|---|---|---|---|
Prepare Complete Streets Plan | Planning | Jan 2017 | $50,000 | $ 0 | |
Prepare plan that identifies improvements needed to provide for non-motorized transportation and other Complete Streets elements. | |||||
Sidewalk Ramp Replacement | Pedestrian | Feb 2017 | $250,000 | $250,000 | |
Replace approximately 36 non-compliant curb ramps at various locations throughout the city. |
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |