Projects — TIB Project Information
TIB Project Information
Town of Winthrop's Complete Streets Award
C-E-887(001)-1
C-E-887(001)-1
Complete Streets Award
Jan 2017 Selection
FY 2018 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $250,000
County: Okanogan | Legislative District: 12 | Project Length: 0.10 | TIB Engineer: Andrew Beagle | Last Payment Date: 02/27/2017
Project Information
Lead Agency | WINTHROP |
Funding Year | 2018 |
Program | CSP |
Current Phase | Audit |
Legislative District | 12 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.10 mi. |
ADT | 0 |
Functional Class | Local Access |
Type of Work | Pedestrian |
Project Contact | Rocklynn Culp |
Contact Email | planner@townofwinthrop.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 02/27/2017 |
Cultural Resource Assessment |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 01/27/2017 | |
Delayed Project Date | 07/01/2019 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | ||
Bid Auth. Approval | ||
Construction Approval | 01/27/2017 | 02/16/2017 |
Project Closeout | 09/01/2018 | 10/02/2019 |
Audit Date | 10/31/2019 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 250,000 | 250,000 |
Other Construction | 0 | 0 |
Total Construction | 250,000 | 250,000 |
Total TIB Funding | 250,000 | 250,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
WINTHROP | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Complete Streets Workplan
Item | Type of Work | Date Added | Est. Cost | Actual Cost | Complete |
---|---|---|---|---|---|
Multimodal Plan | Planning | Feb 2017 | $45,000 | $52,013 | |
Complete a multi-modal plan to address bicycle and pedestrian circulation, transit, ADA transition, and overall integration within a complete streets system. | |||||
Downtown Streetscape Study | Planning | Feb 2017 | $20,000 | $ 0 | |
Complete a Downtown Streetscape Study looking at lane configuration, pedestrian and bicycle needs, ADA, parking, signage and lighting. | |||||
Susie Stephens Trail | Pedestrian; Bicycle | Feb 2017 | $75,000 | $164,116 | |
Complete Phase 2 of the multi-use trail that provides a safe bike-ped access alternative to SR20. | |||||
RiverWalk SR 20 Underpass | Pedestrian | Feb 2017 | $80,000 | $12,985 | |
Complete a pedestrian underpass of the SR20 Chewuch River Bridge to facilitate safer pedestrian crossing of SR20 in downtown. | |||||
Downtown Bike Parking | Bicycle | Feb 2017 | $7,500 | $ 952 | |
Install bike parking area for downtown Winthrop - Riverside Ave/SR20 | |||||
Boardwalk to Trail Connection Design | Pedestrian | Feb 2017 | $20,000 | $20,000 | |
Design a pedestrian facility to connect the downtown boardwalks with the entrance to the Susie Stephens Trail. |
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |