Projects — TIB Project Information
TIB Project Information
City of Leavenworth's Complete Streets Award
C-E-850(002)-1
C-E-850(002)-1
Complete Streets Award
March 2022 Selection
FY 2023 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $75,000
County: Chelan | Legislative District: 12 | Project Length: 0.13 | TIB Engineer: Andrew Beagle | Last Payment Date: 06/07/2022
Project Information
Lead Agency | LEAVENWORTH |
Funding Year | 2023 |
Program | CSP |
Current Phase | Construction |
Legislative District | 12 |
Congressional District | 8 |
Federal Route Number | 9999 |
Project Length | 0.13 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Pedestrian |
Project Contact | Tom Wachholder |
Contact Email | twachholder@cityofleavenworth.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 06/07/2022 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 03/28/2022 | |
Delayed Project Date | 03/28/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 05/01/2022 | 05/12/2022 |
Bid Auth. Approval | 05/01/2022 | 05/12/2022 |
Construction Approval | 11/01/2023 | 05/12/2022 |
Project Closeout | 12/01/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 75,000 | 75,000 |
Other Construction | 0 | 0 |
Total Construction | 75,000 | 75,000 |
Total TIB Funding | 75,000 | 75,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
LEAVENWORTH | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Complete Streets Workplan
Item | Type of Work | Date Added | Est. Cost | Actual Cost | Complete |
---|---|---|---|---|---|
Complete sidewalk adjacent to Community Center | Pedestrian | Mar 2022 | $75,000 | $ 0 | |
Installation of concrete sidewalk along the East side of Orchard Street from Evans Street to Birch Street. | |||||
Central Ave Pedestrian Maintenance and Replacement | Pedestrian | Apr 2023 | $75,000 | $ 0 | |
Replace and/or rehabilitate sidewalk panels on Central Avenue from Birch to Evans. If excess grant funding additional sidewalk maintenance on other streets may occur. | |||||
Commercial Street Railing: 3rd to 8th Street | Pedestrian | Jul 2024 | $75,000 | $ 0 | |
Design and construct ped railing along commercial street from 3rd Street vicinity to 8th Street vicinity. |
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |