Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Leavenworth's Complete Streets Award

C-E-850(002)-1

C-E-850(002)-1
Complete Streets Award

March 2022 Selection

FY 2023 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $75,000

County: Chelan   |   Legislative District: 12   |   Project Length: 0.13   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 06/07/2022

Project Information

Lead Agency LEAVENWORTH
Funding Year 2023
Program CSP
Current Phase Construction
Legislative District 12
Congressional District 8
Federal Route Number 9999
Project Length 0.13 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Pedestrian
Project Contact Tom Wachholder
Contact Email twachholder@cityofleavenworth.com
TIB Engineer Andrew Beagle
Last Payment Date 06/07/2022
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   03/28/2022
Delayed Project Date 03/28/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 05/01/2022 05/12/2022
Bid Auth. Approval 05/01/2022 05/12/2022
Construction Approval 11/01/2023 05/12/2022
Project Closeout 12/01/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 75,000 75,000
Other Construction 0 0
Total Construction 75,000 75,000
     
Total TIB Funding 75,000 75,000

Local Funding Partners

Funding Amount Percent
LEAVENWORTH 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Complete Streets Workplan

Item Type of Work Date Added Est. Cost Actual Cost Complete
Complete sidewalk adjacent to Community Center Pedestrian Mar 2022 $75,000 $ 0
Installation of concrete sidewalk along the East side of Orchard Street from Evans Street to Birch Street.
Central Ave Pedestrian Maintenance and Replacement Pedestrian Apr 2023 $75,000 $ 0
Replace and/or rehabilitate sidewalk panels on Central Avenue from Birch to Evans. If excess grant funding additional sidewalk maintenance on other streets may occur.
Commercial Street Railing: 3rd to 8th Street Pedestrian Jul 2024 $75,000 $ 0
Design and construct ped railing along commercial street from 3rd Street vicinity to 8th Street vicinity.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments