Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Othello's Complete Streets Award

C-E-844(001)-1

C-E-844(001)-1
Complete Streets Award

March 2022 Selection

FY 2023 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $400,000

County: Adams   |   Legislative District: 9   |   Project Length: 1.72   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 06/15/2022

Project Information

Lead Agency OTHELLO
Funding Year 2023
Program CSP
Current Phase Construction
Legislative District 9
Congressional District 4
Federal Route Number 9020
Project Length 1.72 mi.
ADT 0
Functional Class Minor
Type of Work Pedestrian
Project Contact Thalia Lemus
Contact Email tlemus@othellowa.gov
TIB Engineer Jonathan Heusman
Last Payment Date 06/15/2022
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   03/25/2022
Delayed Project Date 03/25/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 04/30/2022 06/09/2022
Bid Auth. Approval 04/30/2022 06/09/2022
Construction Approval 04/30/2022 06/09/2022
Project Closeout 12/15/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 400,000 400,000
Other Construction 0 0
Total Construction 400,000 400,000
     
Total TIB Funding 400,000 400,000

Local Funding Partners

Funding Amount Percent
OTHELLO 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Complete Streets Workplan

Item Type of Work Date Added Est. Cost Actual Cost Complete
Biligual Crosswalk Features Pedestrian Mar 2022 $60,000 $60,000
Install bilingual crosswalk features to four (4) intersection on Main Street.
Main Street Pedestrian Street Lighting Pedestrian; Aesthetics Mar 2022 $320,000 $320,000
Complete 5-6 blocks of pedestrian lighting on Main Street.
Bike Lanes Restripe Bicycle Mar 2022 $20,000 $20,000
Stripe bike lanes along 7th Avenue and Scootney Street.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments