C-E-208(001)-1
C-E-208(001)-1
Complete Streets Award
March 2022 Selection
FY 2023 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $300,000
County: Spokane | Legislative District: 4 | Project Length: 0.11 | TIB Engineer: Andrew Beagle | Last Payment Date: 06/15/2022
Project Information
Lead Agency | SPOKANE VALLEY |
Funding Year | 2023 |
Program | CSP |
Current Phase | Audit |
Legislative District | 4 |
Congressional District | 5 |
Federal Route Number | 4033 |
Project Length | 0.11 mi. |
ADT | 0 |
Functional Class | Minor |
Type of Work | Pedestrian |
Project Contact | Adam Jackson |
Contact Email | ajackson@spokanevalley.org |
TIB Engineer | Andrew Beagle |
Last Payment Date | 06/15/2022 |
Cultural Resource Assessment |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 03/28/2022 | |
Delayed Project Date | 03/28/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | ||
Bid Auth. Approval | ||
Construction Approval | 11/01/2022 | 06/14/2022 |
Project Closeout | 06/30/2024 | 02/01/2024 |
Audit Date | 02/01/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 300,000 | 300,000 |
Other Construction | 0 | 0 |
Total Construction | 300,000 | 300,000 |
Total TIB Funding | 300,000 | 300,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
SPOKANE VALLEY | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Complete Streets Workplan
Item | Type of Work | Date Added | Est. Cost | Actual Cost | Complete |
---|---|---|---|---|---|
Park Road Sidewalk Project | Pedestrian | Mar 2022 | $300,000 | $612,943 | |
Install approx. 600 linear feet of new infill sidewalk on the west side of Park Rd. beginning approximately 225 feet south of Nora Ave. and running north to approximately 80 feet south of Baldwin Ave. |
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |