The intersection of 5th and D Street has experienced multiple traffic accidents including injury accidents. The intersection lacks any pedestrian warning signals, ADA compliant ramps, or crosswalks.
Projects — TIB Project Information
TIB Project Information
City of Yakima's Pedestrian improvements
C-E-180(003)-1
C-E-180(003)-1
Pedestrian improvements
Intersection at 5th Avenue and D Street
FY 2026 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $198,300
County: Yakima | Legislative District: 14 | Project Length: 0.01 | TIB Engineer: Jonathan Heusman | Last Payment Date:
Project Information
Lead Agency | YAKIMA |
Funding Year | 2026 |
Program | CSP |
Current Phase | Construction |
Legislative District | 14, 15 |
Congressional District | 4 |
Federal Route Number | |
Project Length | 0.01 mi. |
ADT | 0 |
Functional Class | Principal |
Type of Work | Pedestrian |
Project Contact | Bill Preston |
Contact Email | Bill.Preston@yakimawa.gov |
TIB Engineer | Jonathan Heusman |
Last Payment Date | |
Cultural Resource Assessment | Section 106 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 03/22/2024 | |
Delayed Project Date | 03/22/2027 | |
DAHP Assessment Date | 07/17/2024 | |
Predesign Approval | ||
Design Approval | 05/01/2024 | 05/24/2024 |
Bid Auth. Approval | 07/31/2024 | 06/25/2024 |
Construction Approval | 10/15/2024 | 11/08/2024 |
Project Closeout | 12/01/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 45,000 |
Right of Way | 0 | 0 |
Total Design | 0 | 45,000 |
Construction Engineering | 0 | 76,400 |
Construction Contract | 198,300 | 510,500 |
Other Construction | 0 | 0 |
Total Construction | 198,300 | 586,900 |
Total TIB Funding | 198,300 | 631,900 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
YAKIMA | 62,290 | 9.9% |
WSDOT Funding | 0 | 0.0% |
HSIP | 317,000 | 55.3% |
Complete Streets (C-E-180(002)-1) | 54,310 | 9.5% |
Total Local Funding | 433,600 | 74.7% |
Project Description
Construct bulb outs on 3 corners of intersection of 5th avenue and D Street and add ADA accessible curb ramps on all corners. Extend the No Parking areas on the soutbound lane on 5th Ave to be over 20' from crosswalk to improve sight distance, and add 'No Parking Here to Corner' signs. Install crosswalks, and add crosswalk signage for southbound and northbound traffic on 5th Ave. Install RRFB and push buttons for pedestrians crossing 5th Avenue. Install stormwater facilities to accomodate the curb bulb outs.
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |