City of Yakima's Complete Streets Award
C-E-180(002)-1
C-E-180(002)-1
Complete Streets Award
March 2022 Selection
FY 2023 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $250,000
County: Yakima | Legislative District: 14 | Project Length: 0.17 | TIB Engineer: Jonathan Heusman | Last Payment Date: 06/07/2022
Project Information
| Lead Agency | YAKIMA |
| Funding Year | 2023 |
| Program | CSP |
| Current Phase | Audit |
| Legislative District | 14, 15 |
| Congressional District | 4 |
| Federal Route Number | 4608 |
| Project Length | 0.17 mi. |
| ADT | 0 |
| Functional Class | Collector |
| Type of Work | Pedestrian |
| Project Contact | Bill Preston |
| Contact Email | bill.preston@yakimawa.gov |
| TIB Engineer | Jonathan Heusman |
| Last Payment Date | 06/07/2022 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 03/29/2022 | |
| Delayed Project Date | 03/29/2025 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 04/15/2022 | 05/24/2022 |
| Bid Auth. Approval | 04/15/2022 | 05/24/2022 |
| Construction Approval | 06/15/2022 | 05/24/2022 |
| Project Closeout | 12/31/2024 | 03/27/2025 |
| Audit Date | 03/31/2025 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 0 | 0 |
| Construction Contract | 250,000 | 250,000 |
| Other Construction | 0 | 0 |
| Total Construction | 250,000 | 250,000 |
| Total TIB Funding | 250,000 | 250,000 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| YAKIMA | 0 | 0.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 0 | 0.0% |
Complete Streets Workplan
| Item | Type of Work | Date Added | Est. Cost | Actual Cost | Complete |
|---|---|---|---|---|---|
| Pacific Avenue Sidewalk - 13th Street to Yakima County Justice Center |
Pedestrian | Mar 2022 | $250,000 | $195,376 | |
| Design and construct sidewalk on the south side of Pacific Avenue, completing the missing link. | |||||
| Systemic Pedestrian Improvements, 5th and D Street Intersection Improvements |
Pedestrian | Nov 2024 | $54,310 | $54,624 | |
| Construct sidewalk bulbouts on 3 corners, install curb ramps, crosswalks, RRFB signs and associated storm drainage (C-E-180(003)-1 | |||||
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||