Existing pedestrian facilities throughout the city are inadequate, do not exist, and the public has expressed concern.
Projects — TIB Project Information
TIB Project Information
City of Walla Walla's Citywide pedestrian improvements
C-E-176(003)-1
C-E-176(003)-1
Citywide pedestrian improvements
Multiple Locations
FY 2026 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $564,694
County: Walla Walla | Legislative District: 16 | Project Length: 1.00 | TIB Engineer: Jonathan Heusman | Last Payment Date: 11/19/2024
Project Information
Lead Agency | WALLA WALLA |
Funding Year | 2026 |
Program | CSP |
Current Phase | Construction |
Legislative District | 16 |
Congressional District | 5 |
Federal Route Number | |
Project Length | 1.00 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Pedestrian |
Project Contact | Adam Klein |
Contact Email | aklein@wallawallawa.gov |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 11/19/2024 |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 03/22/2024 | |
Delayed Project Date | 03/22/2027 | |
DAHP Assessment Date | 04/22/2024 | |
Predesign Approval | ||
Design Approval | 05/22/2024 | 05/10/2024 |
Bid Auth. Approval | 06/01/2024 | 07/16/2024 |
Construction Approval | 08/15/2024 | 09/09/2024 |
Project Closeout | 12/31/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 35,586 | 42,329 |
Right of Way | 0 | 0 |
Total Design | 35,586 | 42,329 |
Construction Engineering | 35,586 | 25,000 |
Construction Contract | 470,076 | 821,420 |
Other Construction | 0 | 62,453 |
Total Construction | 505,662 | 908,873 |
Funding Increase | 23,446 | |
Total TIB Funding | 564,694 | 951,202 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
WALLA WALLA | 386,508 | 40.6% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 386,508 | 40.6% |
Project Description
The 2024 Citywide Pedestrian Improvements consist of three separate projects including the Curb Ramp Improvements Project (CRIP), W Moore St Pedestrian Improvements Project (CDBG), and the Citywide RRFB Project (SEE Vicinity Map Attached). The CRIP locations have gaps in pedestrian travel owing to both nonexistent and substandard ADA ramps across the city. The project will construct necessary ADA ramp retrofits inorder to remove sidewalk gaps. The CRIP Project is currently out to bid and is construction ready. The CDBG location has no existing pedestrian facilities. The project will construct ADA ramps and new sidewalk to create a continuous pedestrian accessible route. The CDBG project is currently at 60% Design. The Citywide RRFB Project (CRP) locations are high volume crossings on arterial roadways in the vicinity of public schools, colleges, parks, businesses, and the YMCA.
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |