Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Walla Walla's Complete Streets Award

C-E-176(002)-1

C-E-176(002)-1
Complete Streets Award

March 2022 Selection

FY 2023 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $300,000

County: Walla Walla   |   Legislative District: 16   |   Project Length: 0.20   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 06/07/2022

Project Information

Lead Agency WALLA WALLA
Funding Year 2023
Program CSP
Current Phase Construction
Legislative District 16
Congressional District 5
Federal Route Number 7200
Project Length 0.20 mi.
ADT 0
Functional Class Principal
Type of Work Pedestrian
Project Contact Neal Chavre
Contact Email nchavre@wallawallawa.gov
TIB Engineer Jonathan Heusman
Last Payment Date 06/07/2022
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   03/25/2022
Delayed Project Date 03/25/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 04/30/2022 06/03/2022
Bid Auth. Approval 04/30/2022 06/03/2022
Construction Approval 04/30/2022 06/03/2022
Project Closeout 12/15/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 300,000 300,000
Other Construction 0 0
Total Construction 300,000 300,000
     
Total TIB Funding 300,000 300,000

Local Funding Partners

Funding Amount Percent
WALLA WALLA 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Complete Streets Workplan

Item Type of Work Date Added Est. Cost Actual Cost Complete
Pioneer Park Pedestrian Improvements Pedestrian Mar 2022 $300,000 $300,000
The project includes installation of cement concrete ADA ramps, removal and replacement of hazardous sidewalk, sidewalk infill, improvemeents to stormwater infrastructure, and curb bulb-outs to enhance pedestrian crossings and provide traffic calming measures.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments