Projects — TIB Project Information
TIB Project Information
City of Walla Walla's Complete Streets Award
C-E-176(001)-1
C-E-176(001)-1
Complete Streets Award
Jan 2017 Selection
FY 2018 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $250,000
County: Walla Walla | Legislative District: 16 | Project Length: 0.10 | TIB Engineer: Jonathan Heusman | Last Payment Date: 07/06/2017
Project Information
Lead Agency | WALLA WALLA |
Funding Year | 2018 |
Program | CSP |
Current Phase | Audit |
Legislative District | 16 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.10 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Pedestrian |
Project Contact | Neal Chavre |
Contact Email | nchavre@wallawallawa.gov |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 07/06/2017 |
Cultural Resource Assessment |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 02/07/2017 | |
Delayed Project Date | 07/01/2019 | |
DAHP Assessment Date | ||
Predesign Approval | 12/28/2017 | |
Design Approval | 02/15/2017 | |
Bid Auth. Approval | 02/15/2017 | |
Construction Approval | 02/15/2017 | 03/13/2017 |
Project Closeout | 12/31/2018 | 01/16/2019 |
Audit Date | 01/16/2019 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 250,000 | 250,000 |
Other Construction | 0 | 0 |
Total Construction | 250,000 | 250,000 |
Total TIB Funding | 250,000 | 250,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
WALLA WALLA | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Complete Streets Workplan
Item | Type of Work | Date Added | Est. Cost | Actual Cost | Complete |
---|---|---|---|---|---|
2nd Avenue Sidewalk Infill & Wilbur Ave. Sidewalk Infill | Pedestrian | Dec 2016 | $160,000 | $156,973 | |
Infill missing section of sidewalk along both sides of 2nd Ave. from Tietan St. to Howard St. Also includes infill of missing section of sidewalk along both sides of Wilbur Ave between Alder Street and Olive St. | |||||
Sumach Streetscape | Pedestrian; Aesthetics | Dec 2016 | $28,000 | $18,800 | |
Replace heaved sidewalk and curb/gutter, tree removal and replacement, ADA ramp installation, and brick paver installation along the north side of Sumach Street between 2nd Avenue and Colville Street. | |||||
General City-Wide Sidewalk Repair/Infill | Pedestrian | Dec 2016 | $62,000 | $74,227 | |
Replace sections of damaged or heaved sidewalk, concentrating primarily on areas listed on the sidewalk defect list |
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |