TIB Project Information

City of Walla Walla's Complete Streets Award

C-E-176(001)-1

C-E-176(001)-1
Complete Streets Award

Jan 2017 Selection

FY 2018 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $250,000

County: Walla Walla   |   Legislative District: 16   |   Project Length: 0.10   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 07/06/2017

Project Information

Lead Agency WALLA WALLA
Funding Year 2018
Program CSP
Current Phase Audit
Legislative District 16
Congressional District 5
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Pedestrian
Project Contact Neal Chavre
Contact Email nchavre@wallawallawa.gov
TIB Engineer Jonathan Heusman
Last Payment Date 07/06/2017
Cultural Resource Assessment

Project Schedule

  Target Date Actual Date
Project Selection Date   02/07/2017
Delayed Project Date 07/01/2019  
DAHP Assessment Date  
Predesign Approval 12/28/2017
Design Approval 02/15/2017
Bid Auth. Approval 02/15/2017
Construction Approval 02/15/2017 03/13/2017
Project Closeout 12/31/2018 01/16/2019
Audit Date   01/16/2019
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 250,000 250,000
Other Construction 0 0
Total Construction 250,000 250,000
     
Total TIB Funding 250,000 250,000

Local Funding Partners

Funding Amount Percent
WALLA WALLA 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Complete Streets Workplan

Item Type of Work Date Added Est. Cost Actual Cost Complete
2nd Avenue Sidewalk Infill & Wilbur Ave. Sidewalk Infill Pedestrian Dec 2016 $160,000 $156,973
Infill missing section of sidewalk along both sides of 2nd Ave. from Tietan St. to Howard St. Also includes infill of missing section of sidewalk along both sides of Wilbur Ave between Alder Street and Olive St.
Sumach Streetscape Pedestrian; Aesthetics Dec 2016 $28,000 $18,800
Replace heaved sidewalk and curb/gutter, tree removal and replacement, ADA ramp installation, and brick paver installation along the north side of Sumach Street between 2nd Avenue and Colville Street.
General City-Wide Sidewalk Repair/Infill Pedestrian Dec 2016 $62,000 $74,227
Replace sections of damaged or heaved sidewalk, concentrating primarily on areas listed on the sidewalk defect list

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.