City of Ellensburg's Complete Streets Award
C-E-175(001)-1
C-E-175(001)-1
Complete Streets Award
Jan 2017 Selection
FY 2018 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $250,000
County: Kittitas | Legislative District: 13 | Project Length: 0.10 | TIB Engineer: Jonathan Heusman | Last Payment Date: 07/06/2017
Project Information
Lead Agency | ELLENSBURG |
Funding Year | 2018 |
Program | CSP |
Current Phase | Audit |
Legislative District | 13 |
Congressional District | 8 |
Federal Route Number | 9999 |
Project Length | 0.10 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Pedestrian |
Project Contact | Derek Mayo |
Contact Email | mayod@ci.ellensburg.wa.us |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 07/06/2017 |
Cultural Resource Assessment |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 02/07/2017 | |
Delayed Project Date | 07/01/2019 | |
DAHP Assessment Date | ||
Predesign Approval | 12/22/2016 | |
Design Approval | 02/15/2017 | |
Bid Auth. Approval | 02/15/2017 | |
Construction Approval | 02/15/2017 | 03/01/2017 |
Project Closeout | 12/01/2018 | 05/03/2018 |
Audit Date | 05/21/2018 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 250,000 | 250,000 |
Other Construction | 0 | 0 |
Total Construction | 250,000 | 250,000 |
Total TIB Funding | 250,000 | 250,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
ELLENSBURG | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Complete Streets Workplan
Item | Type of Work | Date Added | Est. Cost | Actual Cost | Complete |
---|---|---|---|---|---|
Willow St Sidewalk Missing Link | Pedestrian | Dec 2016 | $45,220 | $53,966 | |
160' Sidewalk missing link at Seattle Ave, west side | |||||
Helena Ave Sidewalk missing link 1 | Pedestrian | Dec 2016 | $70,115 | $111,305 | |
330' sidewalk missing link at Parklane Ave, south side | |||||
Helena Ave Sidewalk missing link 2 | Pedestrian | Dec 2016 | $99,025 | $111,305 | |
330' sidewalk missing link west of Walnut St., south side | |||||
Idaho Ave sidewalk missing link | Pedestrian | Dec 2016 | $35,445 | $28,529 | |
130' sidewalk missing link east of Abbey Glen Ct, south side |
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |