Projects — TIB Project Information
TIB Project Information
City of Kennewick's Pedestrian Safety Improvements
C-E-173(003)-1
C-E-173(003)-1
Pedestrian Safety Improvements
Multiple Locations
FY 2026 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $192,456
County: Benton | Legislative District: 8 | Project Length: 0.01 | TIB Engineer: Jonathan Heusman | Last Payment Date: 05/13/2025
Project Information
| Lead Agency | KENNEWICK |
| Funding Year | 2026 |
| Program | CSP |
| Current Phase | Audit |
| Legislative District | 8 |
| Congressional District | 4 |
| Federal Route Number | 3406 |
| Project Length | 0.01 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Pedestrian |
| Project Contact | Heath Mellotte |
| Contact Email | heath.mellotte@ci.kennewick.wa.us |
| TIB Engineer | Jonathan Heusman |
| Last Payment Date | 05/13/2025 |
| Cultural Resource Assessment | CRA |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 05/17/2024 | |
| Delayed Project Date | 05/17/2027 | |
| DAHP Assessment Date | 06/14/2024 | |
| Predesign Approval | ||
| Design Approval | 05/31/2024 | 06/20/2024 |
| Bid Auth. Approval | 07/14/2024 | 07/16/2024 |
| Construction Approval | 08/19/2024 | 08/09/2024 |
| Project Closeout | 01/31/2025 | 04/08/2025 |
| Audit Date | 05/13/2025 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 17,600 | 8,250 |
| Construction Contract | 190,720 | 232,320 |
| Other Construction | 0 | 0 |
| Total Construction | 208,320 | 240,570 |
| Funding Surplus | - 15,864 | |
| Total TIB Funding | 192,456 | 240,570 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| KENNEWICK | 48,114 | 20.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 48,114 | 20.0% |
Project Description
Install new ADA ramps and Rectangular Rapid Flashing Beacons (RRFBs) at W. Clearwater Ave/N Johnson St and S. Olympia St/W 36th Ave intersections where no crossings currently exist.
Existing Condition
Project Benefits
- The intersections of W Clearwater Ave @ N Johnson St and S Olympia St @ W 36th Ave are unsignalized with non-compliant ADA ramps.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||