Projects — TIB Project Information
TIB Project Information
City of Spokane's Traffic Calming - Cycle 11
C-E-165(004)-1
C-E-165(004)-1
Traffic Calming - Cycle 11
Multiple Locations
FY 2026 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $415,344
County: Spokane | Legislative District: 3 | Project Length: 1,500.00 | TIB Engineer: Andrew Beagle | Last Payment Date: 06/02/2025
Project Information
Lead Agency | SPOKANE |
Funding Year | 2026 |
Program | CSP |
Current Phase | Audit |
Legislative District | 3, 6 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 1500.00 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Safety |
Project Contact | Kevin Picanco |
Contact Email | kpicanco@spokanecity.org |
TIB Engineer | Andrew Beagle |
Last Payment Date | 06/02/2025 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 05/17/2024 | |
Delayed Project Date | 05/17/2027 | |
DAHP Assessment Date | 05/22/2024 | |
Predesign Approval | ||
Design Approval | 05/31/2024 | 05/30/2024 |
Bid Auth. Approval | 06/01/2024 | 06/10/2024 |
Construction Approval | 06/10/2024 | 06/10/2024 |
Project Closeout | 06/30/2025 | 05/25/2025 |
Audit Date | 06/02/2025 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 40,000 | 180,480 |
Construction Contract | 510,000 | 809,730 |
Other Construction | 0 | 73,480 |
Total Construction | 550,000 | 1,063,690 |
Funding Increase | 1,507 | |
Funding Surplus | - 136,163 | |
Total TIB Funding | 415,344 | 1,063,690 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
SPOKANE | 648,346 | 61.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 648,346 | 61.0% |
Project Description
Various traffic calming treatments at seven locations around the city.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |