City of East Wenatchee's 3rd Avenue Bike and Ped improvements
C-E-161(003)-1
C-E-161(003)-1
3rd Avenue Bike and Ped improvements
N Georgia Ave to N Hanford Ave
FY 2026 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $403,403
County: Douglas | Legislative District: 12 | Project Length: 1,160.00 | TIB Engineer: Andrew Beagle | Last Payment Date: 01/29/2025
Project Information
| Lead Agency | EAST WENATCHEE |
| Funding Year | 2026 |
| Program | CSP |
| Current Phase | Audit |
| Legislative District | 12 |
| Congressional District | 4 |
| Federal Route Number | 5912 |
| Project Length | 1160.00 mi. |
| ADT | 0 |
| Functional Class | Collector |
| Type of Work | Safety |
| Project Contact | Garren Melton |
| Contact Email | gmelton@eastwenatcheewa.gov |
| TIB Engineer | Andrew Beagle |
| Last Payment Date | 01/29/2025 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 05/17/2024 | |
| Delayed Project Date | 05/17/2027 | |
| DAHP Assessment Date | 06/27/2024 | |
| Predesign Approval | ||
| Design Approval | 05/31/2024 | 06/12/2024 |
| Bid Auth. Approval | 07/30/2024 | 06/28/2024 |
| Construction Approval | 08/05/2024 | 08/08/2024 |
| Project Closeout | 12/31/2024 | 01/28/2025 |
| Audit Date | 01/29/2025 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 51,510 | 38,196 |
| Right of Way | 0 | 0 |
| Total Design | 51,510 | 38,196 |
| Construction Engineering | 34,340 | 15,338 |
| Construction Contract | 343,400 | 440,767 |
| Other Construction | 0 | 0 |
| Total Construction | 377,740 | 456,105 |
| Funding Surplus | - 25,847 | |
| Total TIB Funding | 403,403 | 494,301 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| EAST WENATCHEE | 71,345 | 14.4% |
| WSDOT Funding | 0 | 0.0% |
| Eastmont Park District | 19,553 | 4.0% |
| Total Local Funding | 90,898 | 17.7% |
Project Description
Restriping and resin bonded stone surfacing to reconfigure roadway with protected bike lanes. Paving needed for roadway reconfiguration and expense of striping. ADA ramps.
Existing Condition
Project Benefits
- Safety, speed management. Ped/bike mobility and safety.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||