Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Wenatchee's Complete Streets Award

C-E-160(001)-1

C-E-160(001)-1
Complete Streets Award

Jan 2017 Selection

FY 2018 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $250,000

County: Chelan   |   Legislative District: 12   |   Project Length: 0.10   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 07/06/2017

Project Information

Lead Agency WENATCHEE
Funding Year 2018
Program CSP
Current Phase Audit
Legislative District 12
Congressional District 8
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class Local Access
Type of Work Pedestrian
Project Contact Gary Owen
Contact Email gowen@wenatchee.gov
TIB Engineer Andrew Beagle
Last Payment Date 07/06/2017
Cultural Resource Assessment

Project Schedule

  Target Date Actual Date
Project Selection Date   01/27/2017
Delayed Project Date 07/01/2019  
DAHP Assessment Date  
Predesign Approval
Design Approval
Bid Auth. Approval
Construction Approval 02/15/2017 02/14/2017
Project Closeout 12/31/2018 10/31/2018
Audit Date   11/01/2018
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 250,000 250,000
Other Construction 0 0
Total Construction 250,000 250,000
     
Total TIB Funding 250,000 250,000

Local Funding Partners

Funding Amount Percent
WENATCHEE 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Complete Streets Workplan

Item Type of Work Date Added Est. Cost Actual Cost Complete
Pedestrian Master Plan Planning Feb 2017 $25,000 $5,000
Complete development of a pedestrian master plan including necessary ADA transition plan elements addressing accessibility in the public rights of way.
Pedestrian and Bicycle Connections Pedestrian; Bicycle Feb 2017 $100,000 $80,000
Fill sidewalk system gaps prioritizing school walk routes and other criteria identified as high priority in the master plan. Construct multi-use pathways connections.
Illumination System Upgrades Pedestrian Feb 2017 $50,000 $50,000
Improve illumination levels at high pedestrian locations.
Mission/Stevens Landscaping and Pedestrian Connection Pedestrian; Aesthetics Feb 2017 $75,000 $115,000
Soften the look of the Mission/Stevens intersection with landscaping around the old west leg and formalize a pedestrian connection.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments