An at-grade roadway currently provides access to the Bremerton Transportation Center. Periodic surges from off-loading of ferry traffic interferes with pedestrians and local traffic, causing congestion and safety issues.
Projects — TIB Project Information
TIB Project Information
Kitsap County's Bremerton Tunnel
9-W-018(002)-1
9-W-018(002)-1
Bremerton Tunnel
Bremerton Transportation Center to Burwell Street
FY 2008 Urban Corridor Program
Current Phase : Audit
Total TIB Funding : $5,900,000
County: Kitsap | Legislative District: 26 | Project Length: 0.18 | TIB Engineer: Chris Langhoff | Last Payment Date: 06/15/2009
Project Information
| Lead Agency | KITSAP COUNTY |
| Funding Year | 2008 |
| Program | UCP |
| Current Phase | Audit |
| Legislative District | 26 |
| Congressional District | 6 |
| Federal Route Number | 0304 |
| Project Length | 0.18 mi. |
| ADT | 9,900 |
| Functional Class | Principal |
| Type of Work | Reconstruction |
| Project Contact | Neil Campbell |
| Contact Email | CampbeN@wsdot.wa.gov |
| TIB Engineer | Chris Langhoff |
| Last Payment Date | 06/15/2009 |
| Cultural Resource Assessment |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 01/26/2007 | |
| Delayed Project Date | 07/01/2008 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | ||
| Bid Auth. Approval | 01/26/2007 | 01/26/2007 |
| Construction Approval | 05/01/2007 | 09/08/2008 |
| Project Closeout | 06/30/2009 | 07/24/2009 |
| Audit Date | 07/24/2009 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 0 | 3,084,810 |
| Construction Contract | 5,900,000 | 39,905,207 |
| Other Construction | 0 | 1,492,758 |
| Total Construction | 5,900,000 | 44,482,775 |
| Total TIB Funding | 5,900,000 | 44,482,775 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| KITSAP COUNTY | 0 | 0.0% |
| WSDOT Funding | 0 | 0.0% |
| EPA | 1,217,704 | 2.8% |
| Federal Funds | 37,178,771 | 83.6% |
| Bremerton | 186,300 | 0.4% |
| Total Local Funding | 38,582,775 | 86.5% |
Project Description
This project will construct a tunnel that connects the Bremerton Transportation Center to Burwell Street
Existing Condition
Project Benefits
- Reduces congestion by removing 65% of ferry traffic from downtown streets. ;
- ;
- Improves safety by separating ferry traffic reducing conflicts with pedestrians and local traffic.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||