King County's South Park Bridge

9-P-017(023)-1

9-P-017(023)-1
South Park Bridge

S Cloverdale St to East Marginal Way

FY 2010 Urban Corridor Program
Current Phase : Audit
Total TIB Funding : $10,000,000

County: King   |   Legislative District: 11   |   Project Length: 0.42   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 06/26/2014

Project Information

Lead Agency KING COUNTY
Funding Year 2010
Program UCP
Current Phase Audit
Legislative District 11
Congressional District 9
Federal Route Number 1491
Project Length 0.42 mi.
ADT 20,000
Functional Class Principal
Type of Work Bridge
Project Contact Jay Osborne
Contact Email jay.osborne@metrokc.gov
TIB Engineer Greg Armstrong
Last Payment Date 06/26/2014
Cultural Resource Assessment

Project Schedule

  Target Date Actual Date
Project Selection Date   06/25/2010
Delayed Project Date 07/01/2015  
DAHP Assessment Date  
Predesign Approval
Design Approval
Bid Auth. Approval 01/01/2011 12/13/2010
Construction Approval 03/22/2011 04/11/2011
Project Closeout 06/30/2014 06/19/2014
Audit Date   06/26/2014
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 1,000,000 31,034,044
Construction Contract 9,000,000 103,413,994
Other Construction 0 7,260,509
Total Construction 10,000,000 141,708,547
     
Total TIB Funding 10,000,000 141,708,547

Local Funding Partners

Funding Amount Percent
KING COUNTY 37,708,547 26.6%
WSDOT Funding 0 0.0%
Seattle  15,000,000 12.2%
Port of Seattle  5,000,000 4.1%
BRAC Funds  20,000,000 16.3%
STP(U)  15,000,000 12.2%
TIGER 2  34,000,000 27.7%
FMSIB  5,000,000 4.1%
 
 
Total Local Funding 131,708,547 98.5%

Project Description

Construct a new bridge to replace the existing South Park Bridge.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.