This project will complete the final segment of the SE 20th Street/NW 38th Ave. corridor that runs between SE 192nd Ave. in Vancouver and NW Dahlia Drive in Camas. It will reconstruct an old two-lane roadway with drainage ditches on both sides of the road and no bike lanes. The project will satisfy the need for a three-lane arterial roadway and will include construction of concrete sidewalk, a concrete multi-use path and bike lanes.
Projects — TIB Project Information
TIB Project Information
City of Camas's NW 38th Avenue
8-5-185(010)-1
8-5-185(010)-1
NW 38th Avenue
NW Parker St to Grass Valley Park
FY 2025 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $1,692,384
County: Clark | Legislative District: 17 | Project Length: 0.45 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
Lead Agency | CAMAS |
Funding Year | 2025 |
Program | UAP |
Current Phase | Construction |
Legislative District | 17 |
Congressional District | 3 |
Federal Route Number | 7031 |
Project Length | 0.45 mi. |
ADT | 6,654 |
Functional Class | Minor |
Type of Work | Major Widening |
Project Contact | James E Carothers |
Contact Email | jcarothers@cityofcamas.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | |
Cultural Resource Assessment | Section 106 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 01/01/2025 | |
DAHP Assessment Date | 06/23/2024 | |
Predesign Approval | ||
Design Approval | 12/19/2023 | 12/15/2023 |
Bid Auth. Approval | 01/01/2024 | 01/05/2024 |
Construction Approval | 05/16/2024 | 06/23/2024 |
Project Closeout | 03/31/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 198,951 | 794,272 |
Construction Contract | 1,493,433 | 6,592,065 |
Other Construction | 0 | 0 |
Total Construction | 1,692,384 | 7,386,337 |
Total TIB Funding | 1,692,384 | 7,386,337 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
CAMAS | 649,654 | 8.8% |
WSDOT Funding | 0 | 0.0% |
FHWA-STBG Grant Funds from RTC | 5,044,299 | 74.9% |
Total Local Funding | 5,693,953 | 83.7% |
Project Description
The project will complete safety, connectivity and accessibility goals by removing roadside hazards and constructing 0.45 miles of three-lane arterial roadway with a center median/left turn lane, sidewalk, bike lanes, a multi-use path, roadway illumination, wheelchair ramps, and rectangular rapid flashing beacons.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Improves arterial network;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |