NE 137th Avenue was built by Clark County as a rural two-lane roadway with numerous commercial and residential driveways directly accessing the roadway. The roadway has little to no shoulders, no sidewalks, no bicycle facilities, and inadequate illumination. The collision history shows problems with unsafe intersections and issues related to a lack of access management and center turn lane. Much of the corridor drains directly to a culvert with no intervening shoulder. Growth in jobs, increased high-density residential and commercial developments including the Birtcher property, and consideration of increasing congestion on the parallel facilities (162nd and 112th Ave), the arterial travel demand in this corridor requires that the City complete an urban corridor upgrade that provides safe mobility for all modes, provides the appropriate accessibility given the land uses, and strives to retain the integrity of the existing adjacent residential neighborhoods.
Projects — TIB Project Information
TIB Project Information
City of Vancouver's NE 137th Avenue
8-5-184(042)-1
8-5-184(042)-1
NE 137th Avenue
NE 49th St to NE Fourth Plain Blvd
FY 2024 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $3,250,000
County: Clark | Legislative District: 17 | Project Length: 1.00 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
Lead Agency | VANCOUVER |
Funding Year | 2024 |
Program | UAP |
Current Phase | Construction |
Legislative District | 17 |
Congressional District | 3 |
Federal Route Number | 4421 |
Project Length | 1.00 mi. |
ADT | 10,000 |
Functional Class | Minor |
Type of Work | Major Widening |
Project Contact | Hassan Abdalla |
Contact Email | Hassan.Abdalla@cityofvancouver.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | |
Cultural Resource Assessment | Section 106 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 01/01/2024 | |
DAHP Assessment Date | 09/25/2023 | |
Predesign Approval | ||
Design Approval | 02/01/2023 | 12/23/2022 |
Bid Auth. Approval | 10/15/2023 | 09/25/2023 |
Construction Approval | 04/30/2024 | 04/16/2024 |
Project Closeout | 12/31/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 316,913 | 2,541,000 |
Construction Contract | 2,908,587 | 26,117,398 |
Other Construction | 24,500 | 0 |
Total Construction | 3,250,000 | 28,658,398 |
Total TIB Funding | 3,250,000 | 28,658,398 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
VANCOUVER | 15,458,398 | 53.9% |
WSDOT Funding | 0 | 0.0% |
STBG Funds DESIGN | 0 | 0.0% |
STBG Funds ROW | 0 | 0.0% |
STBG Funds CONST. | 9,950,000 | 34.7% |
Total Local Funding | 25,408,398 | 88.6% |
Project Description
This project will complete a full urban upgrade which will provide a safe urban corridor with full multi-modal functionality and provide the needed capacity for growth in the Birtcher development area. At the beginning of 2014 the City of Vancouver completed the urban upgrade project on NE 137th Avenue from NE 28th Street to NE 49th Street, leaving the section of roadway from 49th Street to Fourth Plain as the only remaining section requiring an urban upgrade along 136th / 137th Avenue to NE Fourth Plain Blvd. The project will include building one travel lane in each direction, a center turn lane/median, bike lanes, sidewalks with ADA ramps, roundabouts at identified intersections with multi-use paths, stormwater facilities, streetlights, as well as conduits and fiber installation.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Completes gap;
- Restores structural condition
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |