This project represents the eastern half of the final segment of the SE 1st Street corridor to be improved between SE 164th Avenue and NE 192nd Avenue. Over the last several years, Columbia Tech Center (CTC) has continued to build out with several big box retail pads, a Clark College satellite campus, the Vancouver Clinic, a variety of housing developments, and other commercial and office development, and CTC continues to develop the remaining acreage. Portions of Section 30 and the remaining corners at the intersection of NE 192nd Avenue and SE 1st Street have discussed preliminary development plans. The City of Vancouver recently annexed Section 30 and developed a subarea plan for the district that anticipates 1 million square feet in retail/commercial/office uses, 2 million square feet in employment uses, and over 1,000 residential units. SE 1st Street is inadequate to serve this scale of urban development and increasing traffic volumes with only two lanes little curb, gutter, and sidewalk few safe pedestrian crossings no continuous adjacent sidewalks and no bike facilities.
Projects — TIB Project Information
TIB Project Information
City of Vancouver's SE 1st Street
8-5-184(040)-1
8-5-184(040)-1
SE 1st Street
SE 177th Ave to SE 192nd Ave
FY 2021 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $1,892,899
County: Clark | Legislative District: 18 | Project Length: 0.71 | TIB Engineer: Chris Langhoff | Last Payment Date: 10/11/2024
Project Information
Lead Agency | VANCOUVER |
Funding Year | 2021 |
Program | UAP |
Current Phase | Construction |
Legislative District | 18 |
Congressional District | 3 |
Federal Route Number | 4266 |
Project Length | 0.71 mi. |
ADT | 12,000 |
Functional Class | Principal |
Type of Work | Major Widening |
Project Contact | Anna Dearman |
Contact Email | anna.dearman@cityofvancouver.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | 10/11/2024 |
Cultural Resource Assessment | Section 106 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2019 | |
Delayed Project Date | 01/01/2021 | |
DAHP Assessment Date | 11/03/2014 | |
Predesign Approval | ||
Design Approval | 02/01/2020 | 12/12/2019 |
Bid Auth. Approval | 01/01/2024 | 01/10/2024 |
Construction Approval | 02/29/2024 | 03/08/2024 |
Project Closeout | 12/31/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 200,000 | 1,410,000 |
Construction Contract | 1,800,000 | 9,959,281 |
Other Construction | 0 | 0 |
Total Construction | 2,000,000 | 11,369,281 |
Funding Surplus | - 107,101 | |
Total TIB Funding | 1,892,899 | 11,369,281 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
VANCOUVER | 2,476,382 | 21.8% |
WSDOT Funding | 0 | 0.0% |
USDOT | 5,000,000 | 50.0% |
Private developer | 2,000,000 | 20.0% |
Total Local Funding | 9,476,382 | 91.8% |
Project Description
This project will finish the eastern half of the SE 1st Street corridor between SE 177th Avenue and SE 192nd Avenue The western section between SE 164th Avenue and SE 177th Avenues is anticipated to be complete in June 2021. When completed, the project will connect to recently installed improvements east of SE 192nd Avenue. The design for this segment includes an access-restricted three-to-five-lane section for motor vehicles and separated, off-street protected facilities for people walking and biking. The project also includes lowering the roadway, installing a roundabout at SE 184th Avenue, and installing a new traffic signal at SE 190th Avenue. East of SE 190th Avenue, the roadway will be five motor vehicle lanes with bike lanes and detached sidewalks and additional lanes at the approach to SE 192nd Avenue. Today the roadway is two motor vehicle lanes with gravel shoulders in most areas, although there are spot frontage improvements where development has occurred. Hazardous roadside fixed objects are omnipresent off the gravel shoulder.
Existing Condition
Project Benefits
- Improves safety;
- Improves pedestrian safety;
- Completes gap;
- Removes ADA barriers;
- Builds multimodal facilities
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
Schedule Issues Level 1 Board Delay |
09/25/2023 |