Marvin Road SE is in a rapidly growing area of Thurston County and provides a critical link to Interstate 5 for service members, employees and families traveling to and from Joint Base Lewis McChord and the Interstate 5 corridor. The growth and the corresponding dramatic increase in traffic has strained the road system, to the point where the volume of traffic has exceeded the transportation capacity limits and already the corridor does not meet concurrency requirements. Without needed roadway improvements, future planned development on the corridor will be restricted, congestion will increase, and have a marked impact on an already limited housing supply.
Projects — TIB Project Information
TIB Project Information
Thurston County's Marvin Road SE
8-5-034(017)-1
8-5-034(017)-1
Marvin Road SE
22nd Ave to Union Mills Rd
FY 2024 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $3,750,000
County: Thurston | Legislative District: 2 | Project Length: 0.28 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
Lead Agency | THURSTON COUNTY |
Funding Year | 2024 |
Program | UAP |
Current Phase | Construction |
Legislative District | 2 |
Congressional District | 10 |
Federal Route Number | 5285 |
Project Length | 0.28 mi. |
ADT | 10,100 |
Functional Class | Minor |
Type of Work | Reconstruction |
Project Contact | Scott Lindblom |
Contact Email | scott.lindblom@co.thurston.wa.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 01/01/2024 | |
DAHP Assessment Date | 01/20/2021 | |
Predesign Approval | ||
Design Approval | 02/01/2023 | 01/13/2023 |
Bid Auth. Approval | 02/28/2024 | 04/01/2024 |
Construction Approval | 05/15/2024 | 07/16/2024 |
Project Closeout | 12/31/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 472,794 | 671,694 |
Construction Contract | 3,250,456 | 4,971,616 |
Other Construction | 26,750 | 0 |
Total Construction | 3,750,000 | 5,643,310 |
Total TIB Funding | 3,750,000 | 5,643,310 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
THURSTON COUNTY | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Traffic Impact Fee Program | 893,310 | 15.8% |
Developer Mitigation | 1,000,000 | 14.3% |
Total Local Funding | 1,893,310 | 44.8% |
Project Description
Converting a stop controlled intersection at 19th Ave to a roundabout to improve minor street access and reduce the side street delay that is creating concurrency issues. Access control is proposed between 19th Ave. and Union Mills Rd with a northbound turn lane provided at Union Mills Rd. Bike lanes and pedestrian facilities will be incorporated into the design. Continuous street lighting will be provided along with rectangular rapid flashing beacons on the roundabout crosswalks to improve access for multi-modal corridor users.
Existing Condition
Project Benefits
- Improves arterial network;
- Extends improvements;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |