TIB Project Information

Clark County's NE 152nd Avenue

8-5-006(044)-1

8-5-006(044)-1
NE 152nd Avenue

Padden Pkwy to NE 99th St

FY 2025 Urban Arterial Program
Current Phase : Design
Total TIB Funding : $3,500,000

County: Clark   |   Legislative District: 18   |   Project Length: 0.78   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 05/18/2024

Project Information

Lead Agency CLARK COUNTY
Funding Year 2025
Program UAP
Current Phase Design
Legislative District 18
Congressional District 3
Federal Route Number 4233
Project Length 0.78 mi.
ADT 11,657
Functional Class Collector
Type of Work Major Widening
Project Contact John Mcsherry
Contact Email john.mcsherry@clark.wa.gov
TIB Engineer Chris Langhoff
Last Payment Date 05/18/2024
Cultural Resource Assessment Section 106

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2028  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2024 01/31/2024
Bid Auth. Approval 02/15/2025
Construction Approval 04/22/2025
Project Closeout 01/25/2028
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 120,000 300,000
Right of Way 275,000 747,000
Total Design 395,000 1,047,000
     
Construction Engineering 480,000 1,203,000
Construction Contract 2,487,000 6,217,367
Other Construction 138,000 500,000
Total Construction 3,105,000 7,920,367
     
Total TIB Funding 3,500,000 8,967,367

Local Funding Partners

Funding Amount Percent
CLARK COUNTY 967,367 10.8%
WSDOT Funding 0 0.0%
STBG UL  4,500,000 50.2%
 
 
 
 
 
 
 
Total Local Funding 5,467,367 61.0%

Project Description

This project reconstructs the NE 152nd Avenue from an obsolete two-lane road to modern urban collector with bike lanes and sidewalks. The NE 152ndAvenue/NE 99th Street intersection will be reconfigured from an all-way stop control to a signal-controlled intersection.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments