The south leg of the four-legged, two-way stop, intersection of E Goodlander and Lancaster Roads is the only ingress/egress for the City of Selahs Carlon Park and the Selah High School lower parking lot. The intersection becomes very congested during the peak times when school begins and is let out.
Projects — TIB Project Information
TIB Project Information
City of Selah's E Goodlander Road Signal
8-4-182(008)-1
8-4-182(008)-1
E Goodlander Road Signal
Landcaster Rd Signal
FY 2025 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $538,020
County: Yakima | Legislative District: 13 | Project Length: 0.10 | TIB Engineer: Jonathan Heusman | Last Payment Date: 11/25/2024
Project Information
Lead Agency | SELAH |
Funding Year | 2025 |
Program | UAP |
Current Phase | Construction |
Legislative District | 13, 14 |
Congressional District | 4 |
Federal Route Number | 4710 |
Project Length | 0.10 mi. |
ADT | 2,393 |
Functional Class | Collector |
Type of Work | Traffic Control |
Project Contact | Rocky Wallace |
Contact Email | Rocky.Wallace@selahwa.gov |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 11/25/2024 |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 01/01/2025 | |
DAHP Assessment Date | 02/23/2024 | |
Predesign Approval | ||
Design Approval | 01/01/2024 | 12/18/2023 |
Bid Auth. Approval | 03/15/2024 | 03/07/2024 |
Construction Approval | 04/15/2024 | 04/12/2024 |
Project Closeout | 11/25/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 79,920 | 88,800 |
Construction Contract | 532,890 | 534,000 |
Other Construction | 0 | 0 |
Total Construction | 612,810 | 622,800 |
Funding Surplus | - 74,790 | |
Total TIB Funding | 538,020 | 622,800 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
SELAH | 84,780 | 13.6% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 84,780 | 13.6% |
Project Description
Install a vehicle actuated traffic signal at the intersection of E Goodlander and Lancaster. Widen the entrance to the parking lots to allow for a designated left-turn lane to be installed allowing for right on red movements.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |