Nob Hill Boulevard is a principal arterial that serves as a main east-west corridor for drivers and pedestrian traffic to access southeastern Yakima. As a result of the heavy reliance on Nob Hill, the surface conditions have become poor and continue to deteriorate. The roadway surface contains large longitudinal and transverse cracking along with rutting and spalling throughout the corridor. Most of the existing curb ramps are non-compliant with current ADA standards and are planned to be replaced with this project.
Projects — TIB Project Information
TIB Project Information
City of Yakima's Nob Hill Boulevard Improvements
8-4-180(028)-1
8-4-180(028)-1
Nob Hill Boulevard Improvements
S 4th Ave to S 15th Ave
FY 2025 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $957,599
County: Yakima | Legislative District: 14 | Project Length: 0.81 | TIB Engineer: Jonathan Heusman | Last Payment Date:
Project Information
Lead Agency | YAKIMA |
Funding Year | 2025 |
Program | UAP |
Current Phase | Construction |
Legislative District | 14, 15 |
Congressional District | 4 |
Federal Route Number | 4566 |
Project Length | 0.81 mi. |
ADT | 21,150 |
Functional Class | Principal |
Type of Work | Resurfacing |
Project Contact | Bill Preston |
Contact Email | bill.preston@yakimawa.gov |
TIB Engineer | Jonathan Heusman |
Last Payment Date | |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 01/01/2025 | |
DAHP Assessment Date | 02/08/2024 | |
Predesign Approval | ||
Design Approval | 01/01/2024 | 01/05/2024 |
Bid Auth. Approval | 03/31/2024 | 02/13/2024 |
Construction Approval | 03/15/2024 | 03/25/2024 |
Project Closeout | 12/31/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 197,159 | 233,150 |
Construction Contract | 1,022,161 | 1,022,499 |
Other Construction | 0 | 0 |
Total Construction | 1,219,320 | 1,255,649 |
Funding Surplus | - 261,721 | |
Total TIB Funding | 957,599 | 1,255,649 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
YAKIMA | 298,050 | 23.7% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 298,050 | 23.7% |
Project Description
The proposed improvements consist of milling and overlaying the existing asphalt, crack sealing, new pavement markings, and replacement of non-ADA compliant curb ramps. Improvements include spot pavement repair areas where pavement has completely failed in isolated locations. Curb ramps that cross Nob Hill Boulevard are included in Schedule A as these are required to be replaced with the resurfacing project. Additive Schedule C includes curb ramps at intersecting streets, where curb ramps run parallel with Nob Hill Boulevard and only cross side streets. Additive Schedule B includes synthetic fibers that the City anticipates installing as a test section for comparison to traditional overlay sections.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |