The work included in this application will reconstruct Jackson Street between Magnolia Street and Juniper Street, and Juniper Street from Jackson Street to Monroe Avenue. The corridor serves four schools from preschool to highschool. Limited sidewalk facilities are available. The roadway is also in a state of deterioation beyond maintenance. Subgrade deterioration can be observed at paving joint lines due to the uneveness of the existing asphalt. Approximately 50-percent of the roadway is aligator cracked in less than 1' x 1' squares.
Projects — TIB Project Information
TIB Project Information
City of Toppenish's Jackson Street and Juniper Street
8-4-178(006)-1
8-4-178(006)-1
Jackson Street and Juniper Street
Monroe Ave to Magnolia St
FY 2023 Urban Arterial Program
Current Phase : Design
Total TIB Funding : $1,386,360
County: Yakima | Legislative District: 15 | Project Length: 0.27 | TIB Engineer: Jonathan Heusman | Last Payment Date: 11/25/2024
Project Information
Lead Agency | TOPPENISH |
Funding Year | 2023 |
Program | UAP |
Current Phase | Design |
Legislative District | 15 |
Congressional District | 4 |
Federal Route Number | 6423 |
Project Length | 0.27 mi. |
ADT | 2,041 |
Functional Class | Collector |
Type of Work | Reconstruction |
Project Contact | Dan Ford |
Contact Email | dan.ford@cityoftoppenish.us |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 11/25/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2021 | |
Delayed Project Date | 07/01/2026 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2022 | 02/24/2022 |
Bid Auth. Approval | 12/31/2024 | |
Construction Approval | 01/31/2025 | |
Project Closeout | 07/31/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 151,110 | 167,900 |
Right of Way | 45,675 | 50,750 |
Total Design | 196,785 | 218,650 |
Construction Engineering | 151,110 | 167,900 |
Construction Contract | 1,038,465 | 1,153,850 |
Other Construction | 0 | 0 |
Total Construction | 1,189,575 | 1,321,750 |
Total TIB Funding | 1,386,360 | 1,540,400 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
TOPPENISH | 154,040 | 10.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 154,040 | 10.0% |
Project Description
Reconstruct a narrower cross section including two 12' travel lanes, 6' sidewalk on Jackson Street south frontage and Juniper Street east frontage, upgraded ADA curb ramps, 10' shared use pathway on the north side of Jackson Street, and a flashing beacon. Existing angle parking near the Jackson and Juniper intersection will be converted to parallel parking.
Existing Condition
Project Benefits
- The project benefits will remove and replace a deteriorated roadway which can no longer be stabilized by maintenance efforts. Sidewalks and crosswalks will be added and enhanced to ensure safety to students and the community. This project will be extended in 2024 to Ward Road as part of a funded Surface Transporation (STP) project and as such will be heavily utilized.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |