Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of College Place's NE Damson Avenue

8-4-177(010)-1

8-4-177(010)-1
NE Damson Avenue

Cargill Ave to Rose St

FY 2024 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $1,261,405

County: Walla Walla   |   Legislative District: 16   |   Project Length: 0.71   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 11/14/2024

Project Information

Lead Agency COLLEGE PLACE
Funding Year 2024
Program UAP
Current Phase Construction
Legislative District 16
Congressional District 5
Federal Route Number 7157
Project Length 0.71 mi.
ADT 260
Functional Class Collector
Type of Work Reconstruction
Project Contact Michael Rizzitiello
Contact Email MRizzitiello@cpwa.us
TIB Engineer Jonathan Heusman
Last Payment Date 11/14/2024
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 01/01/2024  
DAHP Assessment Date   11/29/2023
Predesign Approval
Design Approval 02/01/2023 01/13/2023
Bid Auth. Approval 03/15/2024 03/20/2024
Construction Approval 04/30/2024 04/25/2024
Project Closeout 12/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 113,049 215,558
Construction Contract 1,013,657 1,211,003
Other Construction 0 0
Total Construction 1,126,706 1,426,561
     
Funding Increase 134,699  
Total TIB Funding 1,261,405 1,426,561

Local Funding Partners

Funding Amount Percent
COLLEGE PLACE 165,156 11.6%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 165,156 11.6%

Project Description

Improvements on Damson Ave. consist of replacing the failing asphalt surface to maintain a minimum 36-foot wide HMA roadway construct sidewalks, curb, gutter, ADA ramps replace the existing storm water facilities replace the sewer main and sewer laterals and replace utilities where necessary. Additional scope was approved by the TIB board on Dec. 1st, 2023 to perform striping work on Rose St from NE Lambert to NE Carey Ct to change it from a 4 lane to a 3 lane section as well as install an RRFB.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments