City of Walla Walla's E Chestnut Street Roundabout

8-4-176(028)-1

8-4-176(028)-1
E Chestnut Street Roundabout

Approximately 200ft north south east and west

FY 2025 Urban Arterial Program
Current Phase : Design
Total TIB Funding : $1,110,000

County: Walla Walla   |   Legislative District: 16   |   Project Length: 0.10   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 11/19/2024

Project Information

Lead Agency WALLA WALLA
Funding Year 2025
Program UAP
Current Phase Design
Legislative District 16
Congressional District 5
Federal Route Number 7178
Project Length 0.10 mi.
ADT 9,620
Functional Class Minor
Type of Work Traffic Control
Project Contact Mike Laughery
Contact Email mlaughery@wallawallawa.gov
TIB Engineer Jonathan Heusman
Last Payment Date 11/19/2024
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2028  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2024 02/02/2024
Bid Auth. Approval 12/03/2024
Construction Approval 01/29/2025
Project Closeout 12/31/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 191,126 260,000
Right of Way 73,510 100,000
Total Design 264,636 360,000
     
Construction Engineering 110,265 150,000
Construction Contract 735,099 1,000,000
Other Construction 0 0
Total Construction 845,364 1,150,000
     
Total TIB Funding 1,110,000 1,510,000

Local Funding Partners

Funding Amount Percent
WALLA WALLA 400,000 26.5%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 400,000 26.5%

Project Description

The implementation of a roundabout is projected to elevate the Level of Service (LOS) from E to A on opening day and maintain this improved LOS throughout the 2040 design year. The proposed roundabout will be incorporated into the Citys forthcoming Infrastructure Repair and Replacement Program (IRRP) project. The Howard Street IRRP project will replace all water, sewer, and roadway infrastructure between Juniper Street and Bryant Street along Howard Street.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments