City of Pasco's Court Street Roundabout

8-4-174(021)-1

8-4-174(021)-1
Court Street Roundabout

Rd 68 Roundabout

FY 2025 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $1,415,000

County: Franklin   |   Legislative District: 8   |   Project Length: 0.08   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date:

Project Information

Lead Agency PASCO
Funding Year 2025
Program UAP
Current Phase Construction
Legislative District 8
Congressional District 4
Federal Route Number 3524
Project Length 0.08 mi.
ADT 7,500
Functional Class Principal
Type of Work Traffic Control
Project Contact Hollie Geiger
Contact Email geigerh@pasco-wa.gov
TIB Engineer Jonathan Heusman
Last Payment Date
Cultural Resource Assessment Section 106

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 01/01/2025  
DAHP Assessment Date   02/15/2022
Predesign Approval
Design Approval 01/01/2024 01/08/2024
Bid Auth. Approval 03/01/2024 04/03/2024
Construction Approval 04/30/2024 05/07/2024
Project Closeout 12/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 216,982 617,000
Construction Contract 1,383,018 2,333,731
Other Construction 0 0
Total Construction 1,600,000 2,950,731
     
Funding Surplus - 185,000  
Total TIB Funding 1,415,000 2,950,731

Local Funding Partners

Funding Amount Percent
PASCO 0 0.0%
WSDOT Funding 0 0.0%
STBG  1,535,731 46.8%
 
 
 
 
 
 
 
Total Local Funding 1,535,731 46.8%

Project Description

The project will construct a roundabout to appropriately serve current demand and planned mid to long-term needs. The proposed improvements will provide for adequate level of service at the intersection for the study horizon (LOS C by 2045). The project includes utility upgrades to avoid future disruption of proposed surface improvements and adequate lighting for motorized and non-motorized users. Hardscape was incorporated in this project, eliminating needs for permanent irrigation system.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.