The Maple/Walnut one-way couplet is one of the highest traffic volume corridors in the City at over 40,000 ADT, is a T-2 freight route, provides access and connection to/from I-90, leads to/from the Maple St. Bridge crossing of the Spokane River and is the highest volume roadway serving the Northwest portion of the City of Spokane and Spokane County developed areas to the North and Northwest beyond the City of Spokane. Pavement maintenance in the form of a grind and overlay resurfacing is needed to preserve the overall pavement section, extend the life of the overall pavement structure and delay or prevent the need for full depth pavement reconstruction.
Projects — TIB Project Information
TIB Project Information
City of Spokane's Maple Street and Walnut Street
8-3-165(092)-1
8-3-165(092)-1
Maple Street and Walnut Street
5th Ave to 1st Ave
FY 2024 Urban Arterial Program
Current Phase : Design
Total TIB Funding : $920,400
County: Spokane | Legislative District: 3 | Project Length: 0.70 | TIB Engineer: Andrew Beagle | Last Payment Date: 08/19/2024
Project Information
Lead Agency | SPOKANE |
Funding Year | 2024 |
Program | UAP |
Current Phase | Design |
Legislative District | 3 |
Congressional District | 5 |
Federal Route Number | 3879 |
Project Length | 0.70 mi. |
ADT | 40,000 |
Functional Class | Principal |
Type of Work | Reconstruction |
Project Contact | Kevin Picanco |
Contact Email | kpicanco@spokanecity.org |
TIB Engineer | Andrew Beagle |
Last Payment Date | 08/19/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2023 | 12/09/2022 |
Bid Auth. Approval | 11/15/2024 | |
Construction Approval | 01/01/2025 | |
Project Closeout | 12/30/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 75,600 | 126,000 |
Right of Way | 0 | 0 |
Total Design | 75,600 | 126,000 |
Construction Engineering | 90,600 | 151,000 |
Construction Contract | 754,200 | 1,257,000 |
Other Construction | 0 | 0 |
Total Construction | 844,800 | 1,408,000 |
Total TIB Funding | 920,400 | 1,534,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
SPOKANE | 613,600 | 40.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 613,600 | 40.0% |
Project Description
Grind and overlay, surface prep and limited full depth pavement repair, ADA ramps, relocate cantileaver I-90 sign off of sidewalk.
Existing Condition
Project Benefits
- Restores structural condition;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |