City of Spokane's Maple Street and Walnut Street

8-3-165(092)-1

8-3-165(092)-1
Maple Street and Walnut Street

5th Ave to 1st Ave

FY 2024 Urban Arterial Program
Current Phase : Design
Total TIB Funding : $920,400

County: Spokane   |   Legislative District: 3   |   Project Length: 0.70   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 08/19/2024

Project Information

Lead Agency SPOKANE
Funding Year 2024
Program UAP
Current Phase Design
Legislative District 3
Congressional District 5
Federal Route Number 3879
Project Length 0.70 mi.
ADT 40,000
Functional Class Principal
Type of Work Reconstruction
Project Contact Kevin Picanco
Contact Email kpicanco@spokanecity.org
TIB Engineer Andrew Beagle
Last Payment Date 08/19/2024
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 07/01/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2023 12/09/2022
Bid Auth. Approval 11/15/2024
Construction Approval 01/01/2025
Project Closeout 12/30/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 75,600 126,000
Right of Way 0 0
Total Design 75,600 126,000
     
Construction Engineering 90,600 151,000
Construction Contract 754,200 1,257,000
Other Construction 0 0
Total Construction 844,800 1,408,000
     
Total TIB Funding 920,400 1,534,000

Local Funding Partners

Funding Amount Percent
SPOKANE 613,600 40.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 613,600 40.0%

Project Description

Grind and overlay, surface prep and limited full depth pavement repair, ADA ramps, relocate cantileaver I-90 sign off of sidewalk.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.